WBS Summary activity VS LOE activity

Abbas RajabpourMember for 4 years
Created
1
2
0

Hi,

There are sometimes in our projects that we use LOE to put the cost for a WBS with some activities ( Because of an internal agreement)

I wanted to know which one is better and why? ( LOE or WBS Summary)

1 reply

Oldest first
  1. 0
    Santosh Bhat ·

    WBS Summaries will capture

    WBS Summaries will capture the start and end dates from all activities within the WBS Group. LoE (hammocks) allow you to select which activities drive the start and end dates, and they do not need to be within the same WBS group either.