How to create a WBS UDF that can be displayed at Activity level, same as WBS Category can be displayed.

Rodney JonesMember for 14 years 4 months
Created
2
2
0

Hello Everyone,

 

I am wondering how to create a WBS UDF that can be displayed at Activity level, same as WBS Category can be displayed and grouped at Activity Layouts as a column.

Or a WBS code that can be displayed and grouped by at Activity level.

 

Thanks,

 

Rod

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·

    Rodney,WBS UDF is only

    Rodney,

    WBS UDF is only available to assigned on WBS table, if you wanted to Activity Level you can define WBS at Activity UDF. There is no WBS Code or you mean Project Code? Again, Activity Code can be define a WBS definition with hierarchy on single activity code type at activity level. You can create a new WBS definition with hierarchy as up to 20 levels or depending on maximum tree level setting you assigned on Admin preferences.

  2. 0
    Rodney Jones ·

    Closed. Rodel, Yes, I ended

    Closed.

     

    Rodel, Yes, I ended up adding an Activity code. Thanks, Rod