Skip to content

Resource Assignment table copy and paste in Excel

Jean DesjardinsMember for 3 years 7 months
Created
8
3
0

Hi,

I'm trying to copy the resource assignment table and paste it in Excel.

I have divided the labor units by the number of units per period in order to show the number of resources required.

Meanwhile, when pasting in Excel, the labor units are pasted instead of the number of resource.

It seems to copy the database itself instead of what is displayed.

Does anyone know how to extract the number of resources from the resource assignment table?

Thanks 

8 replies

Oldest first
  1. 0
    Rodel Marasigan ·

    Hi Jean,That is correct. You

    Hi Jean,

    That is correct. You can copy paste the unit but not the WYSWYG (using calculate average function).

    If you wish to extract the number of resources required you have two (2) options:
    Option 1: Run a timescale report output to *.csv file which can be open on excel
    Option 2: Copy and paste the unit into excel and use formula to calculate the number of resource (i.e. units/40hrs/week) 

  2. 0
    David Kelly ·

    My advice is not to use

    My advice is not to use copy/paste at all.

    Export the resource assignments using the tabular report wizard, but include the resource calendar for each resource. Then you can use excel to divide the resource quantitis by a factor determined by each resource's  calendar.

    You also have a script to do it again with very few keystokes.

    Email me if you want detailed instructions

  3. 0
    Behrouz Lotfinia ·

    Hi Everybody,I want to import

    Hi Everybody,

    I want to import my resource sheet from excel to P6. 

    I made a sample file in p6.Then I exported it to excel. after that I added my resources below it with same format.I imported it back to p6 successfully, but when I come back to resource sheet, They are not added to my resource sheet. Could you please advise me about it?

    Thanks,

  4. 0
    Behrouz Lotfinia ·

    Hi Everybody,I want to import

    Hi Everybody,

    I want to import my resource sheet from excel to P6. 

    I made a sample file in p6.Then I exported it to excel. after that I added my resources below it with same format.I imported it back to p6 successfully, but when I come back to resource sheet, They are not added to my resource sheet. Could you please advise me about it?

    Thanks,

  5. 0
    Behrouz Lotfinia ·

    Hi Everybody,I want to import

    Hi Everybody,

    I want to import my resource sheet from excel to P6. 

    I made a sample file in p6.Then I exported it to excel. after that I added my resources below it with same format.I imported it back to p6 successfully, but when I come back to resource sheet, They are not added to my resource sheet. Could you please advise me about it?

    Thanks,

  6. 0
    Behrouz Lotfinia ·

    Hi Everybody,I want to import

    Hi Everybody,

    I want to import my resource sheet from excel to P6. 

    I made a sample file in p6.Then I exported it to excel. after that I added my resources below it with same format.I imported it back to p6 successfully, but when I come back to resource sheet, They are not added to my resource sheet. Could you please advise me about it?

    Thanks,

  7. 0
    Behrouz Lotfinia ·

    Hi Everybody,I want to import

    Hi Everybody,

    I want to import my resource sheet from excel to P6. 

    I made a sample file in p6.Then I exported it to excel. after that I added my resources below it with same format.I imported it back to p6 successfully, but when I come back to resource sheet, They are not added to my resource sheet. Could you please advise me about it?

    Thanks,

  8. 0
    Jean Desjardins ·

    Thank you all for the help!

    Thank you all for the help!

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?