Would everyone here use a 3/1 data date for February progress?

John ReevesMember for 13 years 5 months
Created
1
3
0

Would everyone here use a 3/1 data date for February progress? (aside from some stated date like the 15th etc.) - this way it would match Feb. cost data etc., I always heard that the data date line was like 8am or whatever starting time.  I assume in theory that could be changed to 5pm or whatever ending time but I have never heard of anyone doing that.  

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·

    The recommended and standard

    The recommended and standard practice of data date is last working date and time of the reporting cycle.
    Ex: Weekly cut-off = every Friday Cut-off at last working time say 5:00PM 
         Bi-weekly cut-off = alternate Friday Cut-off at last working time say 5:00PM
         Monthly cut-off = Last Friday of the Month at last working time say 5:00PM
         Shutdown per shift = Say at every 6:00PM 1st Shift and 6:00AM 2nd Shift

Log in or join to reply