How to Make PDF from more than one layouts in one go

Mohammad RahmaniMember for 10 years 9 months
Created
1
58
0

Hi All, 

Good morning, 

 

I have below question and I appreciate if you give me any soultion,

 

I have 8 projects and more than 40 contractors and one layout for each, every week I create 40 layouts and 40 repetitive works, is there any way to create PDfs from layouts in one click?

 

I also tried reports but as I have more than one projects open it dosen't save my repoort, and I think it is a bug from Oracle.

 

I look forward for any suggestion and thanks from now.

Stay safe

Mohammad

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    in P6 go to tools then

    in P6 go to tools then reports then batch reports and batch them

Log in or join to reply