Skip to content

How detailed should a programme be....?

S DebMember for 22 years 2 months
Created
37
6
0
To all experienced planners out there.....

i am always intrigued by a question as to how detailed should a programme be ? And to what level is a planning engineer required to prepare a programme...

For one of my recent projects i have prepared a rather detailed programme, however my project manager feels otherwise and wants me to break it further to the extent of working out the dates of each and every pile and each and every pile cap. Isnt this what a site engineer is supposed to be doing ?

On the contrary for another project of mine, my consultant wants me to prepare a programme which should be "not more than 3 pages". He is also against my dividing plastering activities floorwise..no a summarised (lower level) programme is not acceptable to him.

Hope someone of you will have a few tips of me...

Thanks

S.Deb

37 replies

Oldest first
  1. 0
    Tomas Rivera ·
    S Deb:

    Based on my own experience, the level of detail used on a certain project depends on several factors:

    1.- Culture of the organization managing the project. The level of detail of the schedule you would be required to make will be that which the organization or team is used to using or comfortable to use. Not necessarily what the project needs.

    2.- Project management maturity. The lower the maturity the more they tend to ask for more general or less detailed schedules. The higher the maturity they tend to ask or be open for more detailed o sophisticated models which are more in tune with the project needs. Maturity is very closed related to the capacity of the team. Whether they have the tools, the knowledge, the expertise, in house or external.

    3.- Project needs. Project needs are diferent for the diferent phases of the project life. The conceptual, the bidding or budgeting, and the construction phase have all different needs. Also the size and complexity of the project determines the level of detailed of the schedules. And one more important factor is the time frame for the construction of the project. If the project needs to be executed in a very short period of time or can be executed in a very relaxed period of time, the needs will be different.

    4.- Team members requirements. At diferent levels of the hierarchy and at diferent functions of the organization, the level of detailed for the information (including the schedule) will be different. Not only because of their individual responsabilities, but also because of their individual preferences.

    With the above perspective you can understand how the level of detail for the schedule is determined. There might be other factors to consider, but these are the ones I can think of.

    Tomas Rivera
    Altek System
    Detailed scheduling of high performance
    construction projects
  2. 0
    Guy Hindley ·
    One of the rules I use as to how detailed a schedule ought to be is on of understanding and agreeing the "Integration" elements between all the various players on a Project. I am often involved in producing "Integrated programmes", as distinct from single discipline programmes.

    For example on a new aircraft progamme the key integration between the Airframe and the Systems in the aircraft. What are the interface points between the two as the systems and airframe design mature at different rates? The interface points need clearly defining and agreement as to what the interface delivers by both the sending and receiving party needs documenting and agreeing. If we take data which is not mature, then we are introducing risk. The risk is not necessairily a bad thing so long as people are aware and the risk is managed.

    Within an airframe or the systems programme the detail is what is felt appropriate within the team.

    I hope this helps answers your question, or at least gives food for thought.
  3. 0
    Dayanidhi Dhandapany ·
    Tomas Rivera has given a very good explanation on how detail a programme should be. I appreciate him very much..............

    Cheers!!!

    Daya
  4. 0
    Jaco Stadler ·
    I tend to use Three major rules.

    1) The schedule must show me you understand the work.
    2) The schedule must be broken into manageable sections.
    4) Dont mix Trades.

    With other Words (WOW) If you have an activity that is has a duration of 1 year and you tell me you are 50 % complete I would like to be able to see it. If I am unable to see that you are 50 % complete I will ask you to break this up to something smaller.

    Cheers

  5. 0
    Vishwas Bindiganavale ·
    Deb,

    In addition to all the replies for your post, let me highlight examples for ease of your reference.

    Any or all programmes shall confirm to the particular condition of the contract requiring the contractor to propose his logistics and methodology of working. one project that I’m handling had the following instructions stated explicitly in the Conditions of Contract-General Instructions -
    1. No activity shall have a duration longer than 20 days except for procurement, delivery of equipment, etc.
    2. The baseline schedule to show preparation and submittals of materials, shop drawings and as-built drawings, O&M manuals. Commissioning for each system shall be shown seperately.
    3. Constraints shall be given only to the contract’s milestones.
    4. Permanent connections to be included (viz. water, drainage, telephone, power, etc.)
    5. Sub-Frames, Sanitary wares, Iron Mongery to be shown seperately and not to be included with any other activity.
    6. Services works shall be listed seperately for sub-structure ans superstructure stages.
    7. Responsibility of each activity shall be identified with a single performing organisation including interface with the work of other contractors, sub-contractors or the client.

    Another, project required me to prepare a programme showing one-line activity for all the wet trades (irrespective of the no. of floors) and a single one-line activity for the entire services works.

    The message I’m trying to convey here is that, planning engineers/schedulers should adhere to the contractual conditions and try to make good the conditions during the course of the project.

    Also, the advent of the ERP systems in the construction industry has made it imperative for planners to break-down bulk activities into micro-activities. Hence, the requirement of the contract will be very different from the requirement of the internal procedures.

    Happy Planning
  6. 0
    Dayanidhi Dhandapany ·
    Yes Vishwas,

    I also did come across similar things when i was working in malaysia due to fast-track projects. The reason is client wants to have more control on contractor to avoid slipping of works. Yes you are correct, It would be a headache to maintain internal and external versions of schedule for a planner/scheduler but you are telling happy planning at the end.

    Regards

    Daya
  7. 0
    Philip Jonker ·
    Hi Guys,

    I think most of the answers so far has all had good merit.
    So just to go back to S Deb’s subject of piles, I hope I can explain this simply, the activity that normally follows on piles would be cutting back piles and then the pile cap. A Structure may be supported by any number of piles, but normally only one pile cap, why the split down to single piles, if they can be grouped per structure or pilecap. Even if there is a hundred piles it is easy to track and manage.
    Lets take another example, where 20 pumps have to be installed in a pumpstation, the pumps will have split into single units even though the same resource is doing the job, because every pump’s follow on activitis will be different pipelines.
    Hope this helps.

    Regards

    Philip
  8. 0
    Daniel Limson ·
    Very Good Subject! Some contracts are very un-reasonable in that they require you to breakdown your activities to not more than one week duration. However, you can worked around with this type of contracts (afterall we are Planners), for example. for repetitious works, you can create one detailed program and submit this separately as an attachment to your program. And for major commodities, as long as you can define your production rates and resources required to achieved those rates, I believeed a reasonable manager would accept a resonable level of detail. The formula i always apply is KISS. (Keep it simple S?????)

    Cheers,
    Daniel
  9. 0
    Andrew Flowerdew ·
    As detailed as it has to be to convey the information you want it too!!!!!!!!!!!!!!!!!!!!!!!
  10. 0
    Frank Borcherdt ·
    The plan should be a model that initially allows you to validate the proposed delivery method from a time, resource and/or cost perspective. As the project is executed it needs to respond to changes in scope, delays, etc, so you need to break it down to the level of detail that allows the model to forecast the impact of these changes. If you plan at too high a level it is difficult to: -
    accurately reflect the dependencies between activities
    update the progress as the activity is in progress for such a long time
    alter the scope as we have not broken down and quantified the elements allowed for in the original scope

    You will normally improve control and detect slippages earlier by having multiple short activities. The analogy I use is a student writing their thesis, they have six months and usually have a supervisor who regularly asks for an update. If you ask the student after completion when they did the bulk of the work they usually say in the last 4-6 weeks, ask them what they told the supervisor during the process and they usually admit the they overstated their progress. This is human nature and usually has a bearing on the quality of what is produced.

    By breaking the task down into measurable elements, you are able to record the elements that:-
    have been completed
    are in progress
    have not started.

    Summarizing the elements to the higher level more accurately reflects the true progress. These summaries may allow you to meet your contractual reporting requirements and provide the supporting detail if the reported progress is queried.

    My rule of thumb – no activity longer than three update/reporting cycles – therefore can only be in progress for two cycles otherwise it has slipped.

    HTH
  11. 0
    Oscar Wilde ·
    This thread seems to be pretty much like the number of activities

    I like the explanations here much better

    Oscar
  12. 0
    Philip Jonker ·
    Hi Gary,

    The first problem is defining the problem, i.e. the critical areas, and then detailing these ares in what-if situations, and working out the best routes to follow. This is common practice, and as you go along check the less critical areas in the same fashion.

    Regards
  13. 0
    Charleston-Joseph Orbe ·
    Hello to all planners out there,

    Smart project management teams have different needs at each level of details.

    The first level of details are usually for the project executive management team. These groups are not interested in the nuts and bolts of the projects activities. Also they are very busy person that they only need to know the summarize details.

    As the level of project management goes to lower levels, the details also broader.

    At the supervisor level, the programme should be as much detail as possible that the plan has meaning as to what they are doing form supervisors to rank and file personnel.

    Regards,

    Charlie
  14. 0
    Mark Twomey ·
    Hello All,

    Just one additional practical consideration.

    Before embarking, it is important to realise that the greater the level of detail one goes into when preparing a schedule the greater the workload will be when maintaining the schedule there after.
    If you do have have the resources or time to maintain a schedule properly once it has been created it will fall flat on its face.
    It is best to have a schedule with a level of detail than can be maintained by the individual or team that is available.
  15. 0
    Charleston-Joseph Orbe ·
    Hi Mark,

    Experienced and season or veteran Planning Engineers know what to do, including evaluation of the resources available to do planning job or scope or work.

    The fundamental is to know your deliverables to the client and to your company. This is practically the Planning Scope of Work for a particular project. Then you evaluate the resources including the ability, efficiency and effectiveness of that resources to do planning job.

    If you hire labourer to do planning then you may end up working 10 labourers to do the planning job of one expert planning engineer. Or if your planner is swindler to the point of faking his credential, then you may end up doing the work load of that planner.

    In conclusion veteran planning engineer will know what to do to deliver the planning scope of work.

    Cheers,

    Charlie
  16. 0
    Charleston-Joseph Orbe ·
    Hi Clive,

    As you phrase:

    "I have been on a considerable number of projects where the only person looking at the programme is the planning engineer"

    Was the programme done by "Veteran Labourer cum Planner".

    Well it is not surprising.

    As least a planning engineer was looking at the said programme.

    Project Manager don’t look at programme done by labourer specially if the Project Manager got Ph D in construction management or PMP certificate. It is an insult to his educational attainment "a mere labourer giving a vision on how to plan the project".

    The moral here is that programme should be credible and to be prepared by person with credibility and suffcient educational attainment to have impact to the whole construction management team.

    Regards
    Charlie
  17. 0
    Chris Oggham ·
    Hi Clive,

    I read what you said and I totally agree. The programme must have the level of detail required by the team. Too little detail and time is wasted in clarifying anomalies, too much detail and the team can get lost in it.

    As for who produces the programme, as Philip has often pointed out, planning is a mindset. You’ve either got it or you haven’t, and if you haven’t, all the qualifications in the world won’t give it to you. So as you said, it doesn’t really matter if you’re a PhD or a chimpanzee as long as the programme you produce is what the team needs.

    I wonder if, sometimes, some planners get a little bit too impressed with what they see as their own cleverness, and lose sight of the fact that the programme is not an end in itself, but a means to help get the job done. As you pointed out, this means it has to have relevance and meaning to the people who do the work and presented in a form that they can easily understand and use.

    Chris Oggham


  18. 0
    Mark Twomey ·
    Chris/Clive,

    I could not agree more, for example some of the best construction planners I have met come from trades backgounds.

    Best Regards,
    Mark
  19. 0
    Elchie Tan ·
    Agree to all
  20. 0
    Zazi Kumba ·
    Hi Charlie,

    It is nice to know you are active in this forum.

    What is the big deal Charlie? We completed the project without planning software. Every one got a mindset on how to plan, even our labourer did plans.

    I told you dont piss off the white man, they have their own thinking different from us. All you have to do is just enjoy your life.

    I also wanted to know if you can find me a job in any place you work.

    Reards,

    Zazi

  21. 0
    Charleston-Joseph Orbe ·
    Hi Mark,

    You have not yet meet the "BESTEST" of them all.

    IMHO,

    Charlie
  22. 0
    Charleston-Joseph Orbe ·
    Hi Mark,

    You have not yet meet the "BESTEST" of them all.

    And when you meet the bestest, your vey best will only be kids playing around construction site.

    IMHO,

    Charlie
  23. 0
    Charleston-Joseph Orbe ·
    Hi Mark,

    You have not yet meet the "BESTEST" of them all.

    And when you meet the bestest, your vey best will only be kids playing around construction site.

    IMHO,

    Charlie
  24. 0
    Chris Oggham ·
    Hi Mark,

    I agree with you, some of the best planners I have met come from a trades background. As for Charlie`s "bestest", they`re as likely to come from a trades background as anywhere else, it`s the mindset that matters, not the origins.

    Having said that I have met some of the "worstest" as well, and in the main they were overqualified, academically inclined underachievers who were about as much use to the project as a chocolate fireguard.

    Regards

    Chris Oggham
  25. 0
    Charleston-Joseph Orbe ·
    Hello Chris,

    As for you, neither the bestest nor the worstest.

    Have you done real planning?

    Cheers,

    Charlie
  26. 0
    Chris Oggham ·
    Why Charlie,

    Are you thinking of offering me a job? Sorry, no can do. Prior committments and all that.

    Chris Oggham
  27. 0
    Charleston-Joseph Orbe ·
    What the difference between a planer mindset and a real planner (the activities of planning, programming and control professional)

    Do you know?

    Have you been there?

    What are the norms of activities that real planner are doing in there everyday activities?

    What are the planer mindset in there day to day activities
  28. 0
    Se de Leon ·
    Hey guys,

    Am I lost somewhere? Am I disoriented?

    Is this the "Becoming a planner" thread?

    Tell me, please tell me that I’m not really lost.

    Hello, anybody home?

    Se
  29. 0
    Charleston-Joseph Orbe ·
    Hello Clive,

    Gong Chi Fat Chai.

    The gragorian calendar start a new year, the chinese calendar start a new year and a lot of calendar start a new year. New year usher new approach in life. But before the start of New Year inclusive of all calendars will make some punching-punching. This is good for PP.

    OK let start the ball rolling:

    First I was shock your deliverate exclusion of software. Planning without using software is out of my league. I consider it primitive planning. And you are right, labourer cum planer can always talk to labourer, tradesman about planning because that is where the labourer come. Actually, nobody is hindering anyone to talk to anybody. This is a free world. Labourere cum planer dont need educational attainment, no need to know Primavera software, excel chart or Microsoft Project.

    If you will look at the top note it says "PLANNING PLANET, Networking Planning , Programming & Control’s Professionals Around the World". Theses people that PP trying hard to network use software to do planning and control. But then our universe is free, Aliens are welcom. No fingerrpinting, No iris scan, No profiling. The aliens can terorist PP with their brands of Planning technique. Again these is a free world, Only the moderator can police PP.

    Next is ..... There is really no point in furthering this conversation. We know were we stand, PP knows.

    Cheers and enjoy your holiday


    Charlie
  30. 0
    Charleston-Joseph Orbe ·
    Hi there Chris,

    Planning mindset is with everyone since pre-historic times. The ability to communicate the plan is as old as man’s history. All you have to do is read a lot of books including novels (love story, harry potter, lord of the rings, etc.). Reading these books make you aware that planning mindset is with everyone, the hero, the vallians, the sidekick characters.

    The wedding planner got a planning mindset, a family got a planning mindset (husaband and wife planning how many baies to procreate and of course, they have to communicate in achieving there goals). Also the normal household that is the majority dont use Primavera, Microsoft Project Excel Chart to plan the day to day activities to achieve there planning goals.

    A lot of example can be generated that planning mindset is with everyone and the ability to communicate is inherent in a person.


    if you have a time to look at the about notes: PLANNING PLANET Networking Planning, Programming & Control’s Professional Around the World, then you will know that this professional got this planning mindset and the ability to communicate the plans.

    This are the real planners that PP trying to network around the world. But then everyone is welcome including "planers with planing mindset".

    Cheers

  31. 0
    Chris Oggham ·
    Hi Clive,

    Agree with you totally. I must admit I`ve wondered whether Charlie is really like this, or whether he is working to some strange agenda of his own. I am surprised that he can’t see that software is not the whole of planning or even a major part of it. In fact it makes me wonder just how much planning he`s done, but figjam, yes, definitely figjam.

    Regards

    Chris Oggham
  32. 0
    Se de Leon ·
    Hi guys,

    I’ll try my best to bring back the discussion to the real issue at hand.

    How detailed a programme should be?

    IMHO, detailed or not detailed is secondary to me. Maybe tertiary. I believe a programme should be "responsive" to the needs of all project stakeholders, management people, PM, contracts people, construction managers, site engineers, foreman, tradesmen, procurement people, qs, Human resource people etc.

    Responsive meaning, useful and believable from commencement of the project, to tracking and up to close out of contract. If the programme is not reponsive, then what clive said will be true that is, the plan will find itself hanging around the wall of the planning engineer’s room and no one will read it.


    Just my 50 cents.

    Se
  33. 0
    Chris Oggham ·
    Hi Se,

    You’re quite right! Thanks for cutting through the fog and bringing us back to what we should be discussing.

    Chris Oggham
  34. 0
    Philip Jonker ·
    Hi Guys,

    Have been burning the midnight oil lately, hence my lack of participation in the forums. The word mindset keeps on popping up as one of my favourites. What I mean by this is that every person can plan, and they do so on a daily basis, and even for long periods ahead, however this does not make them planners in the sense we are talking about. The mindset I mean is translating these plans from mental ideas on to paper in a format understandable to all. This ability is what makes good planners. You must realise that not not everybody can understand a barchart or s-curve etc, so it is up to the planner to find a way of presenting the program in such a way that the person who need to use it understands it. If the individual prefers a list of dates, give him such a list. Other issues involved is pragmatism, understanding people, hands-on experience etc.
    When I employ somebody as a planner, the first thing I tend to look at is practical experience, then their planning skills, and then their literacy in the particular software. It is easier to to teach a good potential planner the software than to teach a good computor operator planning, however, this is not a strict rule. Dependant on the size of the project, the rules change. If you have a project where a single planner can do the job, or even two planners, I would prefer the practical planner could be an engineer or experienced artisan/foreman etc, however as the project size increases, and the complexity of reporting becomes more difficult, the need arises for a balanced team, where tecnical planning skills and computor skills becomes critical, as you do not want your planners to become bogged down in trying to produce information that somebody with the right computor skills can do in no time. This interaction has major benefits for all, as everybody learns from each other,ie the computor person picks up planning skills and technical experience, and the planners pick up computor skills.
    I believe that sharing knowledge is what makes us tick. On sites I will will normally spend an hour or so with every superintendent/supervisor on a monday morning, looking at their activities for the week, either individualy or in a group, and they will break these activities down in furthe detail on a macro barchart, and agree to what they will achieve, according to which they will be monitored, this means they buy in to their own programmes and teaches them the importance of planning. It also works on their pride, and they will always try to beat their own programs. Hence, working on the mindset of the people who effect the work, helps the schedule.

    The burning of the midnight oil I referred to earlier is that I am currently involved in a major turnkey project, which spans all kind of issues hence long hours and little time to talk.

    The subject of this thread, is something I am learning more about on a daily basis, even though I have had extensive experience in the past. The practical issue is planning something where the conceptual design is in place, but the detail design is in progress, how much detail can you plan into the schedule. The solution is to try and plan for the information that is available, probably somewhere between level 2 and 3. The main thing is trying to get the next six months right, in very good detail, and covering all the activities for this period in as much detail as possible, this includes items, like land aquisition, environmental issues, permits, procurement, tenders, utility diversions, method studies, detail design etc, and planning the construction phase in as much detail as the available information allows. The next phase of planning will be to plan the next six month as detailed as possible and then the next six months.
    The conundrum is that there is no yardstick for the detail in a program. I like using examples, why break a few activities into thousands of activities when it is one. You have ten thousand boiler pipes to be welded by one pool of welders, if you split this into ten thousand activities, multiply this by because, you have measure cut and prep, fit up & tack, weld, NDE, Clear Weld. This means 50 000 activities, whereas you only need five. It then becomes simple, if 5000 welds are completed, the progress is 50%. Keep in mind that for every activity there is atleast two logical links required, and at lest one resource. However there is areas where more detail is required, especially in the instance of interfaces.

    Regards

    Philip

    The answer is be practical, and don’t let factors such as duration and the rest overide or cloud the issues.
  35. 0
    Charleston-Joseph Orbe ·
    Hi Philip,

    Thanks for the best idea.

    I recommend this reply to be the best idea of the week.

    Regards,

    Charlie
  36. 0
    A.Jaffer Sadiq ·

    Hi Dear,Sprit your programme

    Hi Dear,

    Sprit your programme level to 4 part

    Part-1

    Single line grant chart with WBS

    Part-2

    single line with more wbs details

    Part-3

    More wbs with / anyone typical details activates / whole activities

    Note : all activates blow 7-14 days (Except Procurement Details section)

    Part-4

    Resources load /cost load /material

    This final programme [Baseline]

    Jaffer

  37. 0
    Mike Testro ·

    Hi Jaffer This thread is 7

    Hi Jaffer

    This thread is 7 years old - its not good practice to add to long dead threads.

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?