Export/Import Resource loaded programme
In the Open Standard
Catherine BarthelemyMember for 15 years 11 months
- Created
- 1
- 4
0
hello all,
Would anyone know what would cause changes in Unit rates or any other cost discrepancies when export a project to another database?
Our programmes are set to Fixed duration and Units - % complete type is duration.
When importing projects, some of the costs have changed but not others... We have checked all the settings and they all seem to be the same for the resources and activities....
What are we missing?
Any tips?