Urgent Help is needed- UK planner
In the Open Standard
JT
James ThorpeMember for 21 years 1 month
- Created
- 4
- 5
0
4 replies
Oldest first- 0JTJames Thorpe ·I mean to say that since I have not P3 in my Laptop therefore I request all the information in Excel just to see sequence of activities such as
a)Design Finalization
b)Mobilization
c) Procurement
d)Construction Phase
Foundations
Structures
Roofing
Finishes (plumbing, Electrical and
Testing and Commisioning
Handing over
coz in UK, Foundation, Structures and Roofing for buildings and school is different as per location so I need some detailed activoites under these heads for Foundation, Structure and Roofing with 4~5 activities
Just wanna to get these only - 0COCharleston-Joseph Orbe ·Hi David,
Please try the sample projects of planning software, Primavera P3, MS Project, Spider, etc. From these sample projects, visualize your construction sequence of making a school buildings.
You can do it. At the same time, you will develop "critical thinking" the hall mark of planners.
cheers,
charlie - 0DSDaya Sugunasingha ·David Williams
Please find attached a sample of the activities for a PFI funded school I planned in the UK.
I hope that it will be of some use to you!
Regards
Daya
DESIGN OVERVIEW
Planning Application Approved
Scheme Design (GA’s for presentation to Client)
Issue GA’s to School Governors
Meet with School Governors
Agree Scheme Design
Finialise Scheme Design and Freeze
Detail Design
Client / User Group Consultation
Financial Close
Contractor Design
DESIGN DEVELOPMENT
Review Concept Design, Schedules & Accommodation - 1:200’s
Agree Concept Design with School
XXX XXX School agree Furniture and Equipment
1:200 Drawings Production/Completion/Amendment
Co-ordination of Engineering / Costs with Design Team
Review 1:200 Drawings with School Stakeholders
Finalise 1:200 Drawings inc Review Changes and Alterations
Issue Final 1:200 Drawings to School / Design Team
Detailed Design
Conctactor’s Proposals Document
Project Executation Plan
CONSTRUCTION WORKS
Site Logistics and Enablement Works
Set Up Site
Demolition and Site Clearance
Ground Remediation and Vibro-Compaction
Statutory Services and Road Diversions
Construct Road new Yyyy Way/Zzzz Roads etc
Re-route Gas Mains
Re-route Electricity Mains
Water Mains and Fire Hydrant Diversions
Sewer Diversion
Cable TV Diversions
Complete Final Fix, Signs, Lighting etc
Open New Roadway to Public
Works to Xxxx Lane Pavement and Trafic Islands
Make Good / Re-Surface Xxxx Lane incl Line Painting
AREA 1 - TEACHING BLOCK
Construct Column Bases & Underground Drainage
Incomming Services
Concrete Ground Slab
Erect Steel Columns and Beams
Pre-Cast Concrete Planks
Precast Concrete Staircases
Cladding to Atrium Canopy incl Scaffolding
Rebar / Underfloor Heating pipework / Insulation
Concrete and Power Float
Balustrading to Walkways and Staircases
Metsec Jumbo Stud/Insul/Bd to Partitions to Perimeters
Internal Dry Wall Partitions Board one side
Internal Blockwork
External Brickwork and Terra-Cotta Tiles
Doors, Windows, Roof Lights & Atrium Glazing
Roof Insulation and Membrane
External Render
Soil & Vent Stacks and Rainwater Goods
Electrical Installation
Mechanical Services Installation
Suspended Ceilings to corridor/offices
Carpentry and Joinery
Toilet Fit-Out
ICT / Communications Fit-Out
Internal Painting and Decorating
FloorFinishes
Fixtures Fittings & Equipment
Final Clean & Snag
AREA 2 -
Construct Column Bases & Underground Drainage
Incomming Services
Concrete Ground Slab
Erect Steel Columns and Beams
Pre-Cast Concrete Planks
Precast Concrete Staircases
Cladding to Atrium Canopy incl Scaffolding
Rebar / Underfloor Heating pipework / Insulation
Concrete and Power Float
Balustrading to Walkways and Staircases
Metsec Jumbo Stud/Insul/Bd to Partitions to Perimeters
Internal Dry Wall Partitions Board one side
Internal Blockwork
External Brickwork and Terra-Cotta Tiles
Doors, Windows, Roof Lights & Atrium Glazing
Roof Insulation and Membrane
External Render
Soil & Vent Stacks and Rainwater Goods
Electrical Installation
Mechanical Services Installation
Suspended Ceilings to corridor/offices
Carpentry and Joinery
Kitchen Fit-Out
ICT / Communications Fit-Out
Internal Painting and Decorating
FloorFinishes
Fixtures Fittings & Equipment
Final Clean & Snag
AREA 3 -
Construct Column Bases & Underground Drainage
Incomming Services
Concrete Ground Slab
Erect Steel Columns and Beams
Pre-Cast Concrete Planks
Precast Concrete Staircases
Cladding to Atrium Canopy incl Scaffolding
Rebar / Underfloor Heating pipework / Insulation
Concrete and Power Float
Balustrading to Walkways and Staircases
Metsec Jumbo Stud/Insul/Bd to Partitions to Perimeters
Internal Dry Wall Partitions Board one side
Internal Blockwork
External Brickwork and Terra-Cotta Tiles
Doors, Windows, Roof Lights & Atrium Glazing
Roof Insulation and Membrane
External Render
Soil & Vent Stacks and Rainwater Goods
Electrical Installation
Mechanical Services Installation
Suspended Ceilings to corridor/offices
Carpentry and Joinery
Toilet Fit-Out
Kitchen Fit-Out
ICT / Communications Fit-Out
Internal Painting and Decorating
FloorFinishes
Fixtures Fittings & Equipment
Final Clean & Snag
BUT PLEASE NOTE that you have to study the drawings for your project and work out what has to be done, and in what sequence, and with what resources. The drawings will have the answers when you have understood what you are about to build and when you have worked out how you are going to go about it.
GOOD LUCK