Skip to content

Urgent Help is needed- UK planner

James ThorpeMember for 21 years 1 month
Created
4
5
0
I need Uk planner help .

I need one sample project of Building and School being constructed in UK in Excel sheet to see the sequence of activites especially and methodolgy of Works.

plz send me pm urgently

4 replies

Oldest first
  1. 0
    Jose Frade ·
    In Excel ? Never heard.

    What about starting with:
    Basic design
    Detail design
    Procurement/manufacturing
    Construction (Excavation/foundat.construct/etc)
    Finishings
    equipment
    testing
    handover to client

    BR
    JMFrade

  2. 0
    James Thorpe ·
    I mean to say that since I have not P3 in my Laptop therefore I request all the information in Excel just to see sequence of activities such as

    a)Design Finalization
    b)Mobilization
    c) Procurement
    d)Construction Phase
    Foundations
    Structures
    Roofing
    Finishes (plumbing, Electrical and
    Testing and Commisioning
    Handing over

    coz in UK, Foundation, Structures and Roofing for buildings and school is different as per location so I need some detailed activoites under these heads for Foundation, Structure and Roofing with 4~5 activities


    Just wanna to get these only
  3. 0
    Charleston-Joseph Orbe ·
    Hi David,

    Please try the sample projects of planning software, Primavera P3, MS Project, Spider, etc. From these sample projects, visualize your construction sequence of making a school buildings.

    You can do it. At the same time, you will develop "critical thinking" the hall mark of planners.

    cheers,

    charlie
  4. 0
    Daya Sugunasingha ·
    David Williams
    Please find attached a sample of the activities for a PFI funded school I planned in the UK.
    I hope that it will be of some use to you!
    Regards
    Daya

    DESIGN OVERVIEW
    Planning Application Approved
    Scheme Design (GA’s for presentation to Client)
    Issue GA’s to School Governors
    Meet with School Governors
    Agree Scheme Design
    Finialise Scheme Design and Freeze
    Detail Design
    Client / User Group Consultation
    Financial Close
    Contractor Design

    DESIGN DEVELOPMENT
    Review Concept Design, Schedules & Accommodation - 1:200’s
    Agree Concept Design with School
    XXX XXX School agree Furniture and Equipment
    1:200 Drawings Production/Completion/Amendment
    Co-ordination of Engineering / Costs with Design Team
    Review 1:200 Drawings with School Stakeholders
    Finalise 1:200 Drawings inc Review Changes and Alterations
    Issue Final 1:200 Drawings to School / Design Team
    Detailed Design
    Conctactor’s Proposals Document
    Project Executation Plan

    CONSTRUCTION WORKS
    Site Logistics and Enablement Works
    Set Up Site
    Demolition and Site Clearance
    Ground Remediation and Vibro-Compaction
    Statutory Services and Road Diversions
    Construct Road new Yyyy Way/Zzzz Roads etc
    Re-route Gas Mains
    Re-route Electricity Mains
    Water Mains and Fire Hydrant Diversions
    Sewer Diversion
    Cable TV Diversions
    Complete Final Fix, Signs, Lighting etc
    Open New Roadway to Public
    Works to Xxxx Lane Pavement and Trafic Islands
    Make Good / Re-Surface Xxxx Lane incl Line Painting
    AREA 1 - TEACHING BLOCK
    Construct Column Bases & Underground Drainage
    Incomming Services
    Concrete Ground Slab
    Erect Steel Columns and Beams
    Pre-Cast Concrete Planks
    Precast Concrete Staircases
    Cladding to Atrium Canopy incl Scaffolding
    Rebar / Underfloor Heating pipework / Insulation
    Concrete and Power Float
    Balustrading to Walkways and Staircases
    Metsec Jumbo Stud/Insul/Bd to Partitions to Perimeters
    Internal Dry Wall Partitions Board one side
    Internal Blockwork
    External Brickwork and Terra-Cotta Tiles
    Doors, Windows, Roof Lights & Atrium Glazing
    Roof Insulation and Membrane
    External Render
    Soil & Vent Stacks and Rainwater Goods
    Electrical Installation
    Mechanical Services Installation
    Suspended Ceilings to corridor/offices
    Carpentry and Joinery
    Toilet Fit-Out
    ICT / Communications Fit-Out
    Internal Painting and Decorating
    FloorFinishes
    Fixtures Fittings & Equipment
    Final Clean & Snag
    AREA 2 -
    Construct Column Bases & Underground Drainage
    Incomming Services
    Concrete Ground Slab
    Erect Steel Columns and Beams
    Pre-Cast Concrete Planks
    Precast Concrete Staircases
    Cladding to Atrium Canopy incl Scaffolding
    Rebar / Underfloor Heating pipework / Insulation
    Concrete and Power Float
    Balustrading to Walkways and Staircases
    Metsec Jumbo Stud/Insul/Bd to Partitions to Perimeters
    Internal Dry Wall Partitions Board one side
    Internal Blockwork
    External Brickwork and Terra-Cotta Tiles
    Doors, Windows, Roof Lights & Atrium Glazing
    Roof Insulation and Membrane
    External Render
    Soil & Vent Stacks and Rainwater Goods
    Electrical Installation
    Mechanical Services Installation
    Suspended Ceilings to corridor/offices
    Carpentry and Joinery
    Kitchen Fit-Out
    ICT / Communications Fit-Out
    Internal Painting and Decorating
    FloorFinishes
    Fixtures Fittings & Equipment
    Final Clean & Snag
    AREA 3 -
    Construct Column Bases & Underground Drainage
    Incomming Services
    Concrete Ground Slab
    Erect Steel Columns and Beams
    Pre-Cast Concrete Planks
    Precast Concrete Staircases
    Cladding to Atrium Canopy incl Scaffolding
    Rebar / Underfloor Heating pipework / Insulation
    Concrete and Power Float
    Balustrading to Walkways and Staircases
    Metsec Jumbo Stud/Insul/Bd to Partitions to Perimeters
    Internal Dry Wall Partitions Board one side
    Internal Blockwork
    External Brickwork and Terra-Cotta Tiles
    Doors, Windows, Roof Lights & Atrium Glazing
    Roof Insulation and Membrane
    External Render
    Soil & Vent Stacks and Rainwater Goods
    Electrical Installation
    Mechanical Services Installation
    Suspended Ceilings to corridor/offices
    Carpentry and Joinery
    Toilet Fit-Out
    Kitchen Fit-Out
    ICT / Communications Fit-Out
    Internal Painting and Decorating
    FloorFinishes
    Fixtures Fittings & Equipment
    Final Clean & Snag


    BUT PLEASE NOTE that you have to study the drawings for your project and work out what has to be done, and in what sequence, and with what resources. The drawings will have the answers when you have understood what you are about to build and when you have worked out how you are going to go about it.

    GOOD LUCK
    Daya

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?