REFERENCE PLANNING FOR EPC PIPELINE PROJECTS

Sanjeev KoulMember for 19 years 8 months
Created
26
41
0

I have been assigned to prepare a masterplan for EPC pipeline project , starting from feasibility study , engineering , formation and award of EPC contracts,procurement,constructioin/installation , testing and commisioning of pipeline.
I am in need of a sample pipeline project schedule (ie P3 schedule) detailing list of activities (civil,mechanical,piping,instrumentation,electrical etc), durations of activities ,critical activities etc.I need support till i complete this schedule on P3 espacially as i have very limited and basic knowledge only about Primavera.
I shall highly appreciate any aupport in this connection.

26 replies

Oldest first
  1. 0
    Frans Lasut ·
    I need one copy too.

    tamaneden@gmail.com
  2. 0
    Alex Wong ·
    Hi

    What you need is a planner to assist you to complete all these and support you all the way.

    Al
  3. 0
    Mohammed Shafiq ·
    I someone does have a sample programme, can I too have a copy please......
  4. 0
    Nar Thap ·
    Pls send me one copy too at narnor2002@yahoo.com
    thanks
  5. 0
    Ryan Medina ·
    Pls. send me also a copy at kamelyon77@yahoo.com . thanks
  6. 0
    R. Catalan ·
    Hi,

    Please send me also a copy at rrcatalan@hotmail.com

    Thanks a lot.

    R. Catalan
  7. 0
    A M N ·
    Please send me also a copy at tariparast@yahoo.com .
    Best regards
  8. 0
    Forat Faris ·
    Would u Please send me also a copy at foratfaris@yahoo.com
    Best regards
  9. 0
    Kamal Khemchandani ·
    please email me a copy at kamal.khemchandani@exterran.com,
    Thanks a lot.
  10. 0
    Nac Ben ·
    Hi
    I need one copy too.
    nacben@yahoo.fr
    Regards
  11. 0
    Nigel Patrik ·
    Hi

    Can I have a copy please.

    nigelnz@yahoo.com

    Thanks


    Nigel
  12. 0
    Nar Thap ·
    I’d love to have one pls.
    narnor2002@yahoo.com
  13. 0
    Abhay Gujrathi ·
    Hi,

    Can i also have a copy please.

    Cheers

  14. 0
    Abhay Gujrathi ·

    Can i have copy also at abhay.gujrathi@ril.com

    Cheers
  15. 0
    Gerry Ampo ·
    I like also to have a copy for my reference. Can you please send one at gerampo@yahoo.com Thank you.
  16. 0
    Kumar J ·
    Can i also have copy of the same please.

    ooviyan30@yahoo.com

    Thanks / Regards,
  17. 0
    Mike Testro ·
    Hi All

    As far as I can see you are all asking for a copy of something that doesn’t exist yet.

    Best regards

    Mike Testro
  18. 0
    Ahmed Fawzy ·
    please can i have acopy on ahmedfawzy91@hotmail.com
  19. 0
    Shaik Yakub ·
    Can I also have a copy Please

    Yakub_sky@yahoo.co.in
  20. 0
    Naga Bhushan Reddy ·
    Can I pl have a copy of REFERENCE PLANNING FOR EPC PIPELINE PROJECTS on E-mail reddy.nj35@gmail.com
  21. 0
    Echezonachukwu Obiekwe ·

    Hi Atha, If you eventually

    Hi Atha,

     If you eventually develop one for him, could you do me a favour of emailing it to me too. am new this area and would realy like to see what is like.

    thank for contribution, my e-mail is eche742001@yahoo.com

    Thanks,

    Eche

  22. 0
    Echezonachukwu Obiekwe ·

    Hi Atha, If you eventually

    Hi Atha,

     If you eventually develop one for him, could you do me a favour of emailing it to me too. am new to this area of planning and would really like to see what is like.

    thank for contribution, my e-mail is eche742001@yahoo.com

    Thanks,

    Eche

  23. 0
    Rao Rao ·

    Hi, Can I also have a copy

    Hi,

    Can I also have a copy Please

    veta_13@yahoo.com

  24. 0
    Eddy San Gabriel ·

    please send me a sample

    please send me a sample please..

     

    edygabriel@yahoo.com

  25. 0
    Eddy San Gabriel ·

    please send me a sample

    please send me a sample please..

     

    edygabriel@yahoo.com

  26. 0
    Marvin Medina ·

    please send me also..thank

    please send me also..thank you very very much,,,

     

    best regards

     

     

    marvin medina

Log in or join to reply