Sample of MEP plan
In the Open Standard
JF
Jerry FernandezMember for 17 years 6 months
- Created
- 27
- 2
0
27 replies
Oldest first- 0MTMike Testro ·Hi Samer
I apologise if I got your name wrong last time.
There is no simple method of integrating M&E works into a construction project.
The interfaces between the different trades is infinitly variable.
Send me an email to planning.services@xlninternet.co.uk and I will send you a paper that I wrote for the CIOB project of Best Practice for Time Management on the topic of M&E work.
Perhaps this will give you some guidance.
Best regards
Mike Testro - 0JEJulius Espina ·Dear Mike,
Maybe you dont have no idea in mechanical & electrical works. Method statement is totally different with planning. First of all MS is prepared by QA department. I know this because I was once a mechanical QA/QC engineer and I prepared MS,ITPs,checklists,Quality plans,Quality procedures for Mechanical & electrical works.MS is a detailed installation procedure with all attached documents in relation with the euipment to be installed. Secondly,there is planning in MEP works because this is what I do at current,you will also provide EPS,OBS,WBS, activities,resource loading etc.
Regards.
Julius - 0MTMike Testro ·Hi Julius
You are looking at this from the wrong end.
I am not setting down an M&E programme I am putting together what a construction planner needs to know about how to integrate M&E into his programme.
Anyway I will not be sending out any more examples.
Best regards
Mike Testro - 0JEJulius Espina ·Dear Mike,
I know exactly what you want to point out. A simple question must need a simple answer especially to beginners. Jerry only wants a sample of MEP plan and he is not asking a complex one just plain and simple. Thats why we have a MEP planner because he is solely planning on MEP works, and the integration and incorporation will come later and I reiterate Method Statement is another thing.
I hope you get my point. Thanks anyway.
Regards.
Julius
- 0MTMike Testro ·Hi Julius
I am not an M&E engineer but I have enough experience to incorprate M&E works into a construction project using proper bottom up planning principles.
I create a programme for each system in the project and link the start and end to the progress of the structure.
Last year I worked on the New University at Toulouse and there were - for instance - 47 AHU’s each with its own duct system.
So there was 47 different sub charts for each AHU.
The same with all the other sytems in the project.
It took 3 days to set up the whole programme.
Best regards
Mike Testro - 0NANizar Al Akra ·
Greetings to you All, I
Greetings to you All,
I recently joined this amazing network for planners, and i would highly appreciate it if there is anyone who can send me a sample for MEP planning for high rise towers and how it is integrated with civil works and finishing works.
my email address: nizar.al.acra@iccgroupe.com
Thanks and gratitudes for all of you!
Cheers,
- 0PRPrasad Ramanathan ·
Hello JuliusCan you share MEP
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?