Skip to content

Different duration for same Project.

Vipin PeterMember for 8 years 11 months
Created
9
4
0

Hi everybody ,

I am a new user of Primavera.

I am facing an issue regarding total duration of a project which is showing two different duration in two systems. I have imported this project to the second system from the first One where it was created.

I have changed defaulf calender and made it same for both the projects .Still it didnt make any difference.

Later i made unit of time in User Preference as same for the both the projects .

It would be very helpful if somebody can help me to solve this issue..

Vipin

9 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    Do you level project

    Do you level project resources?

    Is finish date different also?

    Does your project include dependency lags?

    Are there multiple calendars?

  2. 0
    Zoltan Palffy ·

    just by changing the project

    just by changing the project to a deflaut calendar this only applies when adding NEW activities. For all of the existing activities they are still on the original calendar assigned to them. You have to ASSIGN the existing activities to the default calendar. Add a column for calendar, filter for ALL, in the calendar column for the first activity at the top select the default claendar and then do a fill down, now re-schedule your project. 

    It is ALWAYS a 2 step process adding a calendar does NOTHING until you ASSIGN  the activities to that calendar and recalcute the schedule.

  3. 0
    Vipin Peter ·

    Hi,Thanks for your Post.In my

    Hi,

    Thanks for your Post.

    In my WBS, activities have three different type calenders are allocated.

    So i think , if i give default Calender for all activities,then i wont get same duration.

    Please correct me if i am wrong.

  4. 0
    Vipin Peter ·

    I have 3 type of calenders

    I have 3 type of calenders allocated for activities.

    Default calender which i put is a different one from these 3 calenders.

    In my master program from which i imported ,Calender settings were done as stated above.

  5. 0
    Zoltan Palffy ·

    Calendars are not associated

    Calendars are not associated with a wbs, calnedars are assigned to an activity and then the activity is assigned to a WBS.

    you determine the durations not the calendars 

  6. 0
    Susanna Kate ·

    Thank you for the solutins

    Thank you for the solutins especially to Zoltan Palffy.

  7. 0
    Zoltan Palffy ·

    glad I could help

    glad I could help 

  8. 0
    Ruel Camaquin ·

    Hi Guys,Let us all be

    Hi Guys,

    Let us all be thankful that we are lucky have the great Zoltan in planning project, although there are others great as he is, but his way of sharing his knowledge in both the software and schedulling is just exceptional.

    Cheers!

    Ruel

  9. 0
    Zoltan Palffy ·

    I do what I can to foster our

    I do what I can to foster our craft. I am a big fan of Training, Education and Mentoring

    I also contribute to the linkedin scheduling forums you can always find me there also.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?