Resource Spread sheet
In the Open Standard
Carlos DominguezMember for 17 years 11 months
- Created
- 3
- 2
0
can someone tell me
if i have a activity with a resource assigned to it as a example the left side of the spead sheet i have my activity and budgeted labour units that says
1 electrician for 2 hrs and on the spread sheet it shows that i need 0 men how come ?
if i have a activity with a resource assigned to it as a example the left side of the spead sheet i have my activity and budgeted labour units that says
1 electrician for 2 hrs and on the spread sheet it shows that i need 0 men how come ?
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?