Primavera Resources

Randy TaylorMember for 17 years 7 months
Created
4
10
0
Under Enterprise Resources,(for resource loading)I have set my Price/Unit category to calculate my internal cost per unit and have dedicated Price/Unit2 category as my revenue for billing.
Going back to the Activites View, can I replace the unit/price cost catagory with the unit/price2 revenue catagory. If so please advise how.

4 replies

Oldest first
  1. 0
    David Maguire ·
    Can it not just be replaced through right clicking on the Activities & selecting columns and editing them?

    Regards

    Maguire
  2. 0
    Randy Taylor ·
    I had wondered the same thing earlier and had tried that but found that the unit/price2 column doesn’t exist in any of the options and can only be viewed if I start at the Enterprise level and step into the Resources.
    Still struggling.
  3. 0
    Karim Mahgob ·
    This column you can find it in the resouce assigment window go to columns and select a column called (Rate Type)....for each assignment you’ll choose the rate type for it
  4. 0
    Randy Taylor ·
    Thanks Karim, that was the piece I was missing. It’s working great!