Primavera 6.0 inporting activity codes

Nancy RobertsMember for 17 years 9 months
Created
6
8
0
Hi all,

I am importing an .xer file (P5) from our vendor. When i import into our system (P6) the codes (activity, resource) do not come over. The vendor has their codes in an EPS level while we generaly have our codes in the Global level. Any help would be appreciated.

thanks

6 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Nancy

    This should be in the Primavera section - not accreditation.

    Best regards

    Mike Testro.
  2. 0
    Dieter Wambach ·
    Nancy
    If you’ll create the EPS codes before importing - exactly same spelling, case-sensitive! - the values automatically will be included.
    For the resource codes I’ll have to check at work. Did you check, if they are included in the xer-file? Maybe a problem of access rights during export.

    Regards
    Dieter
  3. 0
    Dieter Wambach ·
    Nancy
    Resource codes are included within a xer-file ("RCATTYPE"). Codes marked as "secure codes" are not exported.

    Regards
    Dieter
  4. 0
    Nancy Roberts ·
    I have posted in the correct forum category now. Primavera 5/6. Please respond
  5. 0
    Mike Testro ·
    Hi Nancy

    Sorry but I have no Idea how P6 works - I use PowerProject.

    Dieter seems to knwow what he is talking about.

    Best regards

    Mike Testro
  6. 0
    Charleston-Joseph Orbe ·
    actually Nancy,

    This thread got lost. We are busy brainstorming the accreditation issue, then, suddenly out of nowhere you post appear.

    I wish this post will disappear from the main thread and re-routed to the proper thread.

    Cheers,
    Happy Planning and Scheduling