Construction Manpower Histogram
- Created
- 5
- 2
Hi all,
Due to lack of Oil and Gas Onshore Construction planning experience, I have a question the answer to which may seem obvious to someone. The answer may really be obvious, however I would still like to hear your views.
When your onshore construction contractor provides you with their manpower histogram for the duration of the whole project, how can it be verified? In other words, how do you make sure that the contractor has enough people to support the project?
Is the answer here is as simple as knowing the estimated number of manhours provided by the contractor, as well as knowing their work shifts and how many hours they work each day, and then crosschecking with the manpower figures reported in their histograms? Or there is something else?
Thank you in advance.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?