Custom variance column on P6
In the Open Standard
Mohamed AbraarMember for 9 years 7 months
- Created
- 1
- 8
0
Hi All,
I want variance column to show opposite from default ,example baseline start date is 1 April but actual date is 2 April .
The default variance , “ BL-start, “shows minus 1; I want to make a custom field to show the other way, +1 instead of minus 1.
I tried to work around in global change ,it works but the only issue I am facing is if any activity is not started or throwing some random negative 5 digit number “ how to fix this ? “ Do you know the formula for default variance in P6 .
also i want remove the decimal units.