Skip to content

Columns for import to P6

Parisa MohsenizadehMember for 7 years 5 months
Created
12
4
0

Hello everyone,

I have a question; Is it possible to import columns with (*) to P6? I mean columns such as "Physical % Complete" or "Budgeted labor unit".

Thanks in advance

12 replies

Oldest first
  1. 0
    Santosh Bhat ·

    No, fields with an asterix

    No, fields with an asterix are calculated fields within P6 and cannot be imported.

  2. 0
    Zoltan Palffy ·

    yes Budgeted unist is

    yes Budgeted unist is importable any coulmns are what you do is create a work around

    create a udf (uder defined field) and make the field TYPE the same TYPE as the column that you cannot import

    Then import that UDF

    Now run a gloabl change where  the Column that is not importable equals the udf

    I do this if I need to import expected fnish dates which are not importabale 

    There is alwasy a work around 

  3. 0
    Parisa Mohsenizadeh ·

    Hello,Actually I have problem

    Hello,

    Actually I have problem for using global change for columns such as "Budgeted Labor Unit", "Actual Labor Unit" and "Remaining Labor Unit". Is it possible for you to help me in this regard?

    Thank you

  4. 0
    Zoltan Palffy ·

    whats the problem they are

    whats the problem they are importable ?

  5. 0
    Parisa Mohsenizadeh ·

    Hi,Actually I want to use the

    Hi,

    Actually I want to use the Xer File of P6 in order to import it in Primavera Risk Analysis, so I need this information to be in the related columns but due to they have (*) when exporting to excel I can't put the needed information in these columns. Also I couldn't use global change in order to match these columns with the user defined field. Do you have any idea regard this problem?

    Thanks in advance 

  6. 0
    Steven Auld ·

    If you are importing into

    If you are importing into Primavera Risk, why are you using the excel import instead of just importing the xer file?

    You may have to open the xer file in notepad first to change the P6 version if you are using a version that is not compatible with Primavera Risk.

    Steven

  7. 0
    Parisa Mohsenizadeh ·

    Hello Steven,Excuse me

    Hello Steven,

    Excuse me because of not making my question as clear as possible. Actually, I need columns such as budgeted labor unit in Primavera Risk Analysis but the problem is that I have the related information in an Excel file so first I should export from P6 into excel and match the info and then import it in P6 in order to have the columns such as budgeted labor unit in my P6 file. Then it will be ready to import the Xer file into Primavera Risk Analysis, but the problem is that columns such as budgeted labor unit have (*) in exported excel file so it is impossible to put info in them and then import it again in P6. I also have tried a user defiened field (UDF) for making a global change in P6 for budgeted labor unit column but that didn't work too. Is there any work around?

    Thanks in advance

  8. 0
    Santosh Bhat ·

    Parisa,You can copy and paste

    Parisa,

    You can copy and paste into PRA much easier than into P6. Try it, copy a set of columns out of PRA and paste into excel, modify one of the cells and then copy and paste back. Then you can do such for all the data you want to change.

     

    Probably the only useful feature of PRA to make it worth keep using.

  9. 0
    Zhang Haixiang ·

    I think it is impossible. *

    I think it is impossible. * means the data can not be imported.

    e.g."Budgeted labor unit" is summary data calculated from all labor resource.

    you need to import the budgeted unit for each resource, and then P6 will calculate the  "Budgeted labor unit" for you.

  10. 0
    Zoltan Palffy ·

    Zhang you can reate a work

    Zhang 

    you can reate a work around as I have posted below or you can use sdk 

  11. 0
    Zhang Haixiang ·

    It's not that easy.the

    It's not that easy.

    the budgeted labor unit with * is the data exported in TASK sheet of the exported XLS file, which is a summary of all resources assigned to an activity.

    if you use UDF, what number you will put in it, sum of all resources for an act or bugdet of a certain resource of the act?  anyway when you use global change, you need to select which resource will be changed, or P6 will change all resources with that UDF number. 

    Actually the bugdeted Unit in TASKRSRC sheet is importable,you can import budget unit for each resource to get the correct sum.

  12. 0
    Zoltan Palffy ·

    if you read post #8 on Tue,

    if you read post #8 on Tue, 2019-05-07 07:31

    I mentioned that they were importable 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?