Skip to content

Baseline/Updated program of works

Khawaja AhtishamMember for 1 year 5 months
Created
0
7
0

Hi All

I have query that I have recieved Main Contractor Program of works as first program during the execution of project with Baseline dates and Updated/Revised dates together,Program of works also carrying -36 days TF,

I am claiming this program with udated dates as a Baseline program for us with responsibility of -ve TF under Main Contractor...

Is my claim justified !!!or there is better way to handle thesituation !!!!

The program of works fil is provided in pdf format only.

Regards

Khawaja

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?