Revised Baseline Schedule
In the Open Standard
UG
Ulysses GarciaMember for 21 years 1 month
- Created
- 24
- 11
0
When and What is the appropriate time to make a revise baseline schedule considering there is a significant changes in the contract scope,
Is it during the time immediate after the changes of the contract scope or you need to wait until the EOT will be approved.
24 replies
Oldest first- 0DBDavid Bordoli ·tend to think we should stop looking at the programme as a contractual manoeuvring document an treat it as a tool for effective time management of the project.
That means you should produce and update of your programme as soon as the scope changes are known, that way you will be able to schedule and plan your future work load. If you wait until the EoT is awarded, which could be this year next year sometime never, you will have missed out an awful lot of opportunity and would have been trying to run a project against a programme that did not reflect the scope of the works.
- 0JGJames Griffiths ·Hi Ulysses,
The best time to re-baseline is when everyone has agreed all the changes (as soon as possible) - although such changes may not yet have been formally written into the contract.
This situation is always arising, especially in Design work. The problem that we encounter is the fact that it can be very difficult to differentiate between a proper scope change and a natural evolution of the design itself. Not only that, but it can takes months for the client to agree on such changes. As a result, and in order to continue making progress, we often have to work on the amended design without a formal change having been fully agreed or incorporated into the contract. This is why we have to be very strict and keep records of all such communications.
Ultimately, we have to be extremely careful in order to avoid "scope-creep" - otherwise we find ourselves massively overspending and monitoring a project against a baseline that is so far out-of-date that it has little value. The ideal situation is to have everything agreed and incorporated into the contract BEFORE re-baselining - but practical implementation often does not allow you such luxury - so as long as there is some formal or written reference to the change, then it’s best to re-baseline as soon as possible.
Cheers.
James. - 0ADA D ·Hi David, help please,
Whenever there is significant change in scope of work, then we sent a letter for EOT stating the:
1. New planned events need to be incorporated into the program and their effects
2. Planned Delay events as per the Master Construction programme and their effects.
3. Mitigated delay events.
So, say in the present project I am working, there are 22 major events wherein we have asked for EoT. But, does it mean that we shall make a revised baseline program evertime (with every change) or shall we just add on the EoT durations after say 90-100 days.
What would you recommend in this scenario.
Please advise
Cheers,
Raviraj - 0KMKarim Mounir ·Hi David,
I think that you use the original programme (as a formal document) in preparation of the revised programme, which can only be prepared after granting of EOT not before.
The best I can do (in the case of delay in approval of the EOT) is to have a proper and precise data for the changes (or even to prepare an internal schedule to reflect the changes).
So in case of delays from employer/engineer side then I shall claim for EOT (which can lead to further compensation) ASAP and later on incorporate the changes in the original programme (if approved).
Regards,
Karim - 0UGUlysses Garcia ·Hi to all,
The other alternative is to developed a fragnet datas based from the client additional changes of scope and let it approved to established timetable of the changes for EOT approval .
I believed that not until the EOT has been approved the fragnet cannot be inserted in the schedule.
cheers, uly - 0APAndrew Pearce ·Am I missing something? I think David has the right idea.
1. The original baseline is the original plan based on the original estimate, drawings spec etc. (the basis for the contract)
2. As Planners we maintain the current plan by adding actual data and reviewing logic to reflect ANY changes that may occur. This may include substantiation of EoT claims.
3. We can create additional baselines at any time, but untill an EoT is granted the original baseline must be the basis of any comparitive reporting.
As planners we should spend most of our time concentrating on what is to the right of the data date (time now) line. - 0ADA D ·I think everybody is missing what david is saying, Plz note:
"If you wait until the EoT is awarded, which could be this year next year sometime never, you will have missed out an awful lot of opportunity and would have been trying to run a project against a programme that did not reflect the scope of the works."
Which is true many times!!
- 0APAndrew Pearce ·Surely you dont RUN YOUR PROJECT against a baseline?
The baseline reflects the plan at project commencement. You run a "LIVE" schedule which WILL allways be different to the baseline. A comparison between the baseline and your current plan will give you the ammunition for EoT’s assuming reason for variation is recoverable under whatever form of contract you are using.
Each time the scope of your project changes your current plan will change and give a revised completion date, that is how you substantiate your EoT, Yes?
To complete a project Successfully YOU DO NOT NEED A BASELINE!
To complete a project Successfully YOU NEED ACCURATE CURRENT INFORMATION !
- 0UGUlysses Garcia ·To all,
Knowing that the revision is made mainly because there is a significant changes in work scope.
The question is how do we treat or handle the out of sequence activity during updating.
Do we let it remain as it is , or we may change the logic for the out of sequence activities.
- 0KCKongChung Chan ·Hi Andrew,
At any point in the project , we should know ’where we should be at’ and ’where we are at’
’where we should be at’ will be indicated by the Baseline Program or modified Baseline (if major changes dictated by significant changes in work scope)
’where we are at’ will be indicated by updated program.
- 0APAndrew Pearce ·I dont totally disagree with you guys, the point I was trying to make is that once the project is "live" the base line is purely historical. It was the route we intended to take and is used as you quite rightly say for comparison with the current plan.
Also as planners we should concentrate on looking ahead, if the project changes and it will/does our job is to re plan/schedule the project to the earliest completion and in that task the baseline is no longer relevant. (other than as a point of reference.
Think of the baseline as a paper print of the original contract programme and only change it when the contract completion date is changed by an extension of time. (But keep a copy of the original baseline!)
I believe that a project has one current plan and a series of baselines produced as and when extensions of time are awarded. - 0GAGhaith Al-Hiyari ·I believe it is imperative to revise a baseline while preparing the Extension of time, as the extension of time should be evaluated in terms of the original baseline.
How will the Engineer evaluate your entitlement if you do not produce the revised baseline showing the delay events while applying for an extension of time
The revised program is not a derivative of an extension of time, it is the other way around.
Besides; if you had a propper baseline program with propper logic, delay events and external factors can be easily entered into the program seperately.baseline and revised baseline should not differ much (network wise)unless additional work is in the picture..... - 0KCKongChung Chan ·All programs, even the best program, will be a collection of assumptions, educated or a stab in the dark, from the durations used and logic links to approximate the reality that you are trying to model.
Those assumptions made must always be tested, and the best acid test by far will be the events that took place against what the program predicted.
Updates to me must never be just the mechanical filling in of percentages done and ASD/AFDs. Its also a forensic disection of what had gone by so far and the portion of baseline used to forecast that. You cannot be more right in the future if you do not wish to know how wrong you were in the past and why you were wrong in the past.
Since program consist of recurring sequences, lessons learned of the past can be reincorporated into similar recurring sequences or activities yet not done for better forecasts in the future. Or additional resources/manpower/sheer will power be brought to bear such that those durations on site will be achieved as intended in the program. And activities missed in program made that lead to real life delays be incorporated back into that program.
After all, even if baseline program is disregarded, surely the updated program is indeed the same baseline program in first place. Surely one will like to have the updated program more accurate in future even if one should want to disregard the baseline.
Also in an ’updated program’ , the delays are kind of ’incorporated’ into the program. At every week, things are back ’on schedule’.
Which made me exclaimed at site meetings where only updated programs were used as to "Why is this project 3 months late when every week we are back ’on schedule’ with the updated program each week!"
And if we are to say we are ’early’ , or we are ’late’ , or we are ’on program’, surely that must be in relation to what is planned int he first place, aka Baseline Program.
Only by knowing at any point in time, where we should be at (from Baseline), and where we are actually at(from updated program), can we then make more effective usage of resources in our control to bring the project to where we want it to be at.
- 0KCKongChung Chan ·Ghaith,
I did not have much interest in the original thread as can be noted by my earlier absence though I lurk and read.
Depending on which side of the fence I am on (as owner rep, or as contractor) my approach might be very different. I also do not like hypothetical situations where rules and contractual clauses are not known and might change about as the debate continued.
Threads do change in that sub thread can appear as it did in this thread. Feel free to ignore all that I wrote or to chastise me as you just did.
Are you a moderator here to safeguard purity of threads? Or you just love to take a hit at me?
- 0GZGhassan Zihri ·A Contractor can not make modifications (logic, sequence of work…) to a baseline approved by the Engineer.
Throughout the execution of a project, when modifications to original scope occur with negative time impact, the Contractor is entitled to incorporate these changes to the updated baseline (showing actual dates & updated regularly) in order to highlight the forecast of the projected new completion date.
During a Time Claim evaluation, the importance in showing actual dates in a Revised Updated Baseline (or schedule) is to provide evidence to the Engineer that the works not affected by the change order were executed as per original plan.
Regards,
- 0GAGhaith Al-Hiyari ·Modifications to an Original Scope require a revised baseline incorporating such changes, as the additions / Ommisions are not reflected in the baseline program, and thus the original baseline does not incorporate these changes andtherefore; their dirct effect on the project in total cannot be shown (if any).
An updated baseline program without incorporating the additional works might show the effect of the new works on other activities (maybe), but still you need to revise the baseline, incorporate the additions / ommisions evaluate the effect on the project completion.
The next step would be is to insert actual dates on the revised baseline (update) the revised baseline inorder to show that un affected works has commenced as per the original plan (if this is the case).
If I were the Engineer or the Client; I would ask for both as it helps in pointing out any concurrent delays and thus the evaluation of cost incurred.
While it is in (my opinion)...that the logic will remain the same....as a logic is not dependant on scope rather than on relations, the sequence might change as it is a matter of preference, sequence changes all the time ...but it does not affect the logic, because in theory, there is only one logic, the correct logic, while sequence becomes a matter of preference that can change without intersecting with the logical relationships.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?