Progress Reporting

William CaluzaMember for 24 years 9 months
Created
22
6
0
My boss gave me an article from the Association of Project Manager’s Publication titled "Reporting Good Progress is Simple", issue March 2002. The author has mentioned 3 "simple" charts in reporting progress for clients to easily understand. (The text and sample charts are attached to this e-mail).

These are :
1. Planned Progress Method
2. Progress Tracking Chart
3. Line of balance

My question and I seek your advise:

1. Is the above items can be produced using Primavera software? If not, anybody knows which software. and How?

I would highly appreciate any response regarding this. Thanks in advance.

-william

22 replies

Oldest first
  1. 0
    Kyu-Hoon Kwon ·
    I’m pleased to discuss regarding progress reporting with you.
    In my case, I had used Primavera to produce planned progress by using Primavera Menu "Resource","Resource Curve" and "Tablar Resource Report". But I felt that it was insufficient for planned progress,progress measuring and tracking. So I myself have developed Progress Reporting System called SaPIS (Schedule and Progress Integration System). The main concept and logic of planned progress method is tha same as Primavera, such as Calendar,resource,resource curve,activity codes etc. The system can provide you some reports as follow;
    1) Progress Planned Report(Weekly and Monthly)
    : by Project Total and by WBS COde.
    2) Progress Summary and Detail Report
    (Showing Planned vs. Actual Progress of summary
    code and activity)
    3) Progress Detail Achieve Report .
    (Showing Activity and Sub-Activity Progress)
    For more detail information of this system, visit homepage "http://myhome.hananet.net/~khkwon6" and download Demofile in homepage menu "SaPIS"-"Download Demo"

    I hope this sytem would be helpful to you.

    K.H.Kwon
  2. 0
    Tomas Rivera ·
    The attachments do not seem to be anywhere. Could you send them to me directly to my e-mail address? Can somebody tell us if we can send attachements with the forum messages?
  3. 0
    Tomas Rivera ·
    Thanks William.

    I received the attachments directly to my e-mail address.

    I am almost certain that the Line of Balance chart cannot be reproduced in Primavera. The cases in which this chart is used are projects like a simple line of production: one activity after the other. If you have this type of project you can plan and track it very quickly and easily with this method (it can be considered a method like CPM) without using computers at all.
    The Progress Tracking Chart can be reproduced using Tools/Graphic Reports/Resource and Cost. You will need to use a common resource for all the activities of the project, like cost. Go through the windows to specify what you want, it is straightforward. But if you need help, drop me a line.
    The Planned Progress Method can be reproduced in Primavera in the same place as the above chart. This is my prefered way of reporting progress. I use a dummy resource called "progress" with a quantity per activity equal to the duration of the activity. This way is not very reliable if you have schedules with a small number of activities. This chart shows the range in which actual progress should fall. But bear in mind that this is just one side of the coin: if your progress is within the range, it does not necessarily mean that the project is on track.
  4. 0
    Forum Guest ·
    Hi

    You should have a look at IPSO for reporting. Reports can be defined using virtually any data held by the server and even calculations performed on the fly. You can get a copy for evaluation from www.omnis-group.com
  5. 0
    Mike Harvey ·
    Visit hpcconsult.co.uk and look under 'Planning Academy it may help? Regards Mike Harvey
  6. 0
    Zq qz ·

    Progress Reporting

    Hello William ,
    Can you directly send those attachment to my e-mail (donatom@rcjubail.gov.sa). regards
  7. 0
    Forum Guest ·
    Hi,

    Sorry we currently can’t include attachments with the forum messages.

    Do you think this would be useful?
  8. 0
    Nestor Principe ·
    Certainly, it would be helpful.
  9. 0
    Ronald Winter ·
    Allowing attachments would also be a great way to spread viruses and copyright material like songs and scheduling software.
  10. 0
    Bernard Ertl ·
    Perhaps having a file downloads section separate from the forums (where members may upload files for consideration) would be a better way to go?

    Files could be checked before listing to ensure appropriateness. Also, files would be easier to find for all members since you would not have to search for (or stumble across) a particular thread to find it.

    Bernard Ertl
    InterPlan Systems Inc. - Project Management Software, Project Planning Software
  11. 0
    Tara Muddappa ·
    Dear William,

    Could you please mail me the attachments to my email ID : tara.b.m@seccadia.co.ae.

    I look forward to have this soon.

    Thanks and regards,

    Tara muddappa
  12. 0
    Joe Mansour ·
    Hello William,

    Please include me on your addressee for your attachments.
    My e-mail: ecobuild@inco.com.lb

    I may help with some other ways of reporting.

    Thanks
  13. 0
    Shahzad Munawar ·
    Please send me the attachments on
    My e-mail: shahzadmn@yahoo.com

    I may help with some other ways of reporting.
  14. 0
    Soheil Jafari ·
    Hi,
    Also Please send me the attachments on
    My e-mail: s.jafari@iranpm.com
  15. 0
    Mehdi Rashidi Alangeh ·
    Hi,
    I’m pleased to discuss regarding progress reporting with you.
    In this case, I had used Primavera to produce some your items. But some of this item such as L.O.B created in customise software ( ec in excel with macro usage).

    Regards
  16. 0
    Rahul Mulik ·
    William,

    I would be happy to have that attachment in my mail box,\
    mulikrahul@nmx.biz
    as I am working on first 2 reports through Primavera itself, so I can add few points to you.

    Cheers & Regards,
    Rahul Shamrao Mulik
  17. 0
    Devamalya De ·
    Dear,
    Plzzz send a copy of the attachment 2 me also at: dev2k5@gmail.com


    Regards,
    Devamalya De
  18. 0
    Christian Adrian De Vera ·
    Since the donwload section is still under consideration by the moderators I think, at the moment, it would be better if the sender could upload it to another site and post the link here so that others could download it too...

    Just an idea..

    Christian
  19. 0
    Pmkb . ·
    PP Members may post files (please .ZIP them first) in the PMKB Templates/Files forum.

    Stacy
    Project Management Knowledge Base
  20. 0
    Hans Masuy ·
    Just my opinion:

    Actually, progress reporting is depending to the client’s requirement. Basically, it will briefly stated in the ITB and most of the planner / project manager in my company will refer to the spec required. However, we always discuss further with the client regarding any possible modification can be done.

    H.M
    Project Manager
  21. 0
    JV Amande ·


    i think progress reporting more done using excel format, however source data must come from the primavera program. Using excel will help your big boss understand and easily interpret the flow and the progress of your project, rather than submitting report directly printed from primavera.

    anyway, can you please send me a copy as well..

    maraksot_2004@yahoo.com

    thanks..

  22. 0
    Samer Zawaydeh ·
    Dear JV,

    This post is 8 years old. I am sure that no one is going to send you anything.

    With kind regards,

    Samer