Suretrak - Weekdays and Weekend days Count

K.k. ReddyMember for 23 years 8 months
Created
3
2
0
I am creating a project schedule with SureTrak,
The following is the issue,
Any help will be appreciated. Thank you.

I want to count weekdays and weekends.
For one item, I put in Start_Date 01/28/03 and 62 days to complete.
End_Date is suppose to be 03/31/03, but SureTrak is giving me
End_Date as 04/23/2003. Is there any way I can count all days,
both weekdays and weekends, and put in End_Date as 03/31/03
on the screen, as calculated.




3 replies

Oldest first
  1. 0
    Steven Oliver ·
    Check your calender, if Sat/Sun are classed as non working, either change them to working days, or create a new calender with the working days you require.

    Same goes for holiday days.

    have fun
  2. 0
    K.k. Reddy ·
    Steven, No luck.
    Even I created new calendar, with 7 days 8 hrs day week.
  3. 0
    Ed van der Tak ·
    Hi,

    While checking your question in suretrack I found the following :

    1) Check the exceptions option in the calendar, it could contain dates!
    2) The global calendar has effect on using calendar no. 1. Make this global calendar "empty" ie 7days/week and define exceptions in the others 1,2,3,4 etc calendars. Only days applicable for ALL calendars should remain in the global calendar.

    I hope this solves your problem.

    Plan for the best,

    Ed van der Tak
    ARAM Planning Consultants
    The Netherlands