Total Float
In the Open Standard
Anil GuptaMember for 23 years 2 months
- Created
- 11
- 3
0
Hi All
I am facing a unique problem .Looking for advise.
I have developed a EPC schedule for one construction porject having total duaration of 540 days.
Few engineering and construction activities i am getting float of around 200 days. I feel relationships are justified.
E.g i have submittal for water heater which is showing float of 200 days bacause ..delivery is loacal and product is needed on site at the last only.But all submittals have to be made within 30% of project duration.Thats why high float coming..and many more activities like this.
My problem is our consultant wants these flaots to be reduced (By any means).I don’t want to reduce these floats by giving unjust relationships as it may jeopardise our interests at later stage..Please advise what could be best way out of it.Also FS with lag is not allowed to be used..
Regards
Anil
I am facing a unique problem .Looking for advise.
I have developed a EPC schedule for one construction porject having total duaration of 540 days.
Few engineering and construction activities i am getting float of around 200 days. I feel relationships are justified.
E.g i have submittal for water heater which is showing float of 200 days bacause ..delivery is loacal and product is needed on site at the last only.But all submittals have to be made within 30% of project duration.Thats why high float coming..and many more activities like this.
My problem is our consultant wants these flaots to be reduced (By any means).I don’t want to reduce these floats by giving unjust relationships as it may jeopardise our interests at later stage..Please advise what could be best way out of it.Also FS with lag is not allowed to be used..
Regards
Anil
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?