Quality Indicator

Forum GuestMember for 17 years 8 months
Created
5
2
0
Hi All

In working with schedules and costs we use SPI and CPI as indexes for project controls.I am wondering if there is an index of quality,I was thinking like rework hours/budgeted hours what do you think,what is the quality approach for projects contrls.

Thanks in advance
AA

5 replies

Oldest first
  1. 0
    Mk Tse ·
    May I know what SPI and CPI stand for?
  2. 0
    Dinesh Kumar ·


    SPI is Schedule performance index
    CPI is Cost performance index

    Regards

    Dinesh
  3. 0
    Bernard Ertl ·
    Budgetplanned costs across a specified time period; the project’s estimated costs
    BCWSBudgeted Cost for Work Scheduled to be completed within a given time period; [Budget] X [percent of the duration to the current date]; planned costs (budget) up to the current date
    ACWPActual Cost of Work Performed during a given time period; money spent up to the current date
    BCWPBudgeted Cost for Work Performed; Earned Value; the dollar amount of work that was actually accomplished; [Budget] X [percent complete]
    Schedule VarianceSV = BCWP - BCWS; the value of what you have accomplished to date, versus what you planned to have accomplished to date
    Cost VarianceCV = BCWP - ACWP; the value of what you have accomplished to date, versus what you have spent to date
    Schedule Performance IndexSPI = BCWP / BCWS
    Cost Performance IndexCPI = BCWP / ACWP

    Earned Value and Performance Indicator Definitions

    Bernard Ertl
    InterPlan Systems Inc. - Project Management Software, Project Planning Software
  4. 0
    Mk Tse ·
    It seems nobody to use a programme for qulaity checking. The reason may due to the additional amount of quality related activity. As AA’s stated, how to reflect the re-work hour? Either a group of repeated or a proportional to the actual duration of the original. This make the network complex.
    In P3, either user CDF to hold the proportion or introduce re-work activities. For P3e/c v4.0, may be simple just add one more issue/checklist against activity to create the Index.
  5. 0
    David Waring ·
    The only time when I have seen something similar used was on site, where resourced programmes were being progressed, and the data exported and integrated with actual cost information in Excel.
    Part of the validation routine involved reasons for cost and time changes from planned to actual results - this included quality performance (errors, etc.) as part of the report.
    It could possibly be done by categorising resources spent into Useful, Rework, etc. - but that would mean updating the resource allocation when entering progress- never a good idea!

Log in or join to reply