Key Performance Indicators

Andrew OwensonMember for 20 years 11 months
Created
15
2
0
Hi Guys

I have been asked to produce a set of KPI’s for Planners. They will be used to monitor performance and will be used as a basis of bonuses. This system will be intended to be used in both tender and construction programming. I have thought of a few

Team leader satisfaction with the overall service provided
Team leader satisfaction with product
Programme delivery (within agreed timescale)
Programme accuracy
Progress moniotoring

Any ideas

Andrew

15 replies

Oldest first
  1. 0
    Steven Oliver ·
    What ?

    Someone wanting to monitor what Planners are doing?

    We cant have that.

  2. 0
    Mohammed Abo El Magd ·
    Andrew,
    These are good points, but you should give low weights to the first two points, that both of them depends on human moods which is not always stable.

    For the forth point, How do you plan to measure the accuracy?
  3. 0
    Shah Shams Alam ·
    Andrew,

    Indeed these are good monitoring points. Mohammed is right in pointing out that first two points depend on human mood, but they are very essential. you can also consider taking feedback from end user of the plans. I mean execution team or field personel.


  4. 0
    Andrew Owenson ·
    Thanks for your replies

    I was thinking that maybe I could use most of the KPI’s for both Precon (tender) and Construction phases.

    I would really like to have about ten points of reference though. ?

    Cheers

    Andrew
  5. 0
    Sukumaran Subaramaniyan ·
    Well general appraisal is always better than specific appraisal, i.e:
    a) Communication
    b) Team work
    c) Efficiency
    d) Capability
    e) Understanding
    f) etc.....

    Management can use the general info for salary increment and bonuses payout. As for promotion, management can use the specific info as you mentioned earlier.

    Regards.
  6. 0
    Steven Oliver ·
    How many points do I get for Insolence, Intolerance and Sarcasm ?
  7. 0
    Andrew Owenson ·
    Clive

    Its a contractor. The KPI’s will be used as part of the appraisal process. What is wrong with having key points as a measuring device? People who are doing their job to their best abilities should not be worried about being assessed. I Personally have no problem being assessed via a stuctured appraisal process.

    Anybody else got any thoughts ?


    Cheers

    Andrew
  8. 0
    Chris Oggham ·
    Andrew,

    You’re right, there is nothing wrong with having Key Performance Indicators, sometimes they’re called Key Success Indicators showing just how well you’re doing your job. Whatever you decide on as the KPIs you should try to ensure that they are SMART, Specific, Measurable, Achievable, Realistic, Time-related.

    That way you avoid any recriminations about unfairness, or dependence on somebody’s opinion, which can cause problems.

    Chris Oggham
  9. 0
    Andrew Owenson ·
    Clive

    100 lines - I must behave myself in class.


    Cheers


    Andrew
  10. 0
    Andrew Owenson ·
    Mohammed

    Sorry I missed your point regarding the 4th point - accuracy

    What I meant by this was does the programme accurately reflect the scheme - the scope on the drawings, bills etc. I take on board the general comment by everyone about peoples perception rather than fact. My concern is that what else can a planner be measured against?

    Cheers

    Andrew
  11. 0
    Mohammed Abo El Magd ·
    Andrew
    Oh,,, now I got it. I thought you mean how applicable was the plan and what was the deviation between actual and the original plan, is it with in acceptable range or beyond that. By the way, you could consider that one of your KPI points.

    Sorry for the delayed response

    Regards
  12. 0
    Andrew Owenson ·
    Mohammed

    How would you be able to differentiate between the accuracy of the planner’s programme and the site’s delays, not claimable delays but mistakes, lack of coordination etc


    Cheers

    Andrew
  13. 0
    Mohammed Abo El Magd ·
    Andrew
    If the deviation between original and actual is 10 to 15% ,That would be acceptable and a success for the planner. If the percentage exceeded this range we have to investigate the reasons for this deviation if it were planning problems or execution problems. It should be a wise investigation not just pointing fingers to each other. The main goal from it should be avoiding such problems in the future.
  14. 0
    Alex Wong ·
    Dear All

    For my team members I prefer look at outcomes and result rather than KPIs

    I looking at KPIs is processes and outcomes is output.

    Input -> Process -> Output
    Effort -> Performance (KPIs) -> Result


    Some time excellent proceesses do not garrantee excellent outputs. So, my staff I would concentrate on the outcomes and outputs.

    Cheers

    Alex
  15. 0
    Amendra Jagoda ·
    Alex,
    You are truly correct, if you plan for productions/manufacturing, in such case, your goal is to achieve the target out put.

    But Construction planning and monitoring progress is different. It is generally through a long period, a year or two or more. During such periods, many unforeseen condition may be generated due to variations, work stoppages, force mageure, submittals and approvals, procurement etc. At the end of the day, to create a cause and effect analysis to adjudicate who is resposible for each delay (employer,engineer or contractor), use of KPI is one of the important estimation method, that you can justify your assessment.

Log in or join to reply