P3 & AutoCAD

Ahmed HamadaMember for 23 years 5 months
Created
8
2
0
hello everybody,
I heard that i can link P3 schedule with an AutoCAD file, in order to show the progress of the project. i mean the activities are linked in somehow with that DWG file. is that possible and how can i do so?

truely,
Ahmed Fouad

8 replies

Oldest first
  1. 0
    Forum Guest ·
    I read a couple years ago that Stanford was developing a software to do that (4D scheduling). I recently heard of a couple packeges already in the market, but still at prohibitive prices.

    The question should go to Primavera; are they considering this technology for upcoming updates?
  2. 0
    Mk Tse ·
    I don’t think Primavera have response on this one. They pay their attention on scheduling, cost and control management. They recommend others to have integration on data with their product.
    Several years ago, Bentley has delveloped a product named simulator for the link up between 3D drawing and P3 project. However, Bentley have pay much effort on this one. I’m not sure their latest product.
    btw, 3 years ago, some universities in China also do some research and development, the data transfer is both ways between programme and drawing.
  3. 0
    Ronaldo de los Reyes ·
    If P3 program will be linked to CADD, it would really improve presentation of the tabular reports, maybe even 3 dimensional graphs. is it possible?
  4. 0
    Zhang Haixiang ·
    I don’t know if there is any ready-made software.
    but you can do it yourself together with programmer.
    AutoCAD support VBA( visual basic for application), which can be used to access P3 file through RA or OBDC to get progress information, then draw whatever you want or just show ready-made hidden objects
  5. 0
    Sunil Kumar ·
    P3 Expedition has the facility of having both Auto cad and P3 but does not solve your purpose of combined presentation.

    Sunil
  6. 0
    Mk Tse ·
    There is off-shelf product for P3 or PEC linked to AutoCAD or MicroStation. First time I view the demo is approx 5 years ago.
    The drawing is either 2D or 3D. If I remember correctly, it is a Bentley’s product.
    I have view another product by chaning on drawing, sequence of activities will be adjusted. The demo is presented by a University in China 2 to 3 years ago and it link Microsoft Project or P3 to AutoCAD only.
  7. 0
    Hannes de Bruyne ·
    Try this one for a demo

    http://www.commonpointinc.com/products/project4d.html
  8. 0
    Guo Shiuch ·

    tyr

    tyr this

    http://gssystem.myweb.hinet.net/gs_project.htm