Climbing System Formwork
In the Open Standard
Stevan SarapaMember for 23 years 4 months
- Created
- 1
- 4
0
Gentlemen,
We are now near to complete L03 level of typical concrete structure (start was in the basement B04 level). From L03 level (large transfer slab) we have two towers, from L04 to L12 level. Typical level consists of two core walls, columns and suspended slab with beams
(see http://groups.msn.com/stevansarapa/documents.msnw).
I have been asked to do exercise , to compare how faster completion of structure will be achieved by hydraulic climbing formwork for the core wall then in case when we use classic frame formwork for core wall.
Please advice for the production rates for self climbing system.
What can be proposed floor sequence?
Regards,
Stevan
We are now near to complete L03 level of typical concrete structure (start was in the basement B04 level). From L03 level (large transfer slab) we have two towers, from L04 to L12 level. Typical level consists of two core walls, columns and suspended slab with beams
(see http://groups.msn.com/stevansarapa/documents.msnw).
I have been asked to do exercise , to compare how faster completion of structure will be achieved by hydraulic climbing formwork for the core wall then in case when we use classic frame formwork for core wall.
Please advice for the production rates for self climbing system.
What can be proposed floor sequence?
Regards,
Stevan
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?