Skip to content

Cold Room & Refrigeration Systems

Sudharma C.Member for 18 years 5 months
Created
11
5
0
Hi there
I am currently involed in the construction planning for a cold room & refrigeration systems.

i am aware of the required interfaces and the natural sequence of works for the construction of a cold room.

however i am not sure of the duration of the activities.

would welcome and appreciate any advice on these from anyone who has experience or comments on this.

thanks
sudharma

11 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Sudharma

    Ask your specialist supplier.

    Best regards

    Mike Testro
  2. 0
    Sudharma C. ·
    thanks for the input.

    Since it is a ’specialist’ work, they are reluctant to divulge the information.

    what i am trying to establish is the reasonable durations it would take to do the works, so that when i assess the program submission, i would be able to tell whether they r being resoanable or ridiculous with their durations.

    rgds
    sudharma
  3. 0
    Mike Testro ·
    Hi Sudharma

    If they are your sub-contractor or prospective sub-contractor it is proper that they should tell you the durations of their work for incorporation in the main programme.

    Insist that they give you the information.

    Best regards

    Mike Testro
  4. 0
    Anoon Iimos ·
    Sudharma,

    here’s some hint:

    1. foundations will take time - the base of your cold storage room has some pipings for drainage.

    2. piping works and the machine room

    3. Insulated panels are easy to install (you might be surprised in 3 days your storage is closed)

    4. if your storage has concrete flooring (then you need time to properly cure the concrete before you can apply the lining - lining takes time as well).

    cheers!
  5. 0
    Mike Testro ·
    Hi Anoon

    You will also need underslab heating to stop frost driven ground heave but Sudharma says he knows all about the interfaces - he just wants to know how long it will take to put the store up.

    A good starting point might be if we knew:

    1. Is it inside another structure - if so is there access for trucks?
    2. How big is it.
    3. Is there only one of them.

    You are right it will not take long to throw up the insulation panels once the structural frame and windposts are in place.

    Its the cooling kit that will take time to install - is this fan driven or water chilled?

    Best regards

    Mike Testro
  6. 0
    Shah. HB ·
    Hi to all
    @Sudharma C
    you could post the activity with quantities then duration could be determined through the discussion in this forum
  7. 0
    Se de Leon ·
    Just to give you an idea, to construct a cold slab with an area of 85’x100’, it would take around 5-6 weeks from slab preparation to pouring.

    Installation of Freezer Panels, around 75LM per day is conservative.

    Pull-down of slab will take around 4-5 days after 28 day curing of the slab. make sure the required dehumidifiers are already working before you pull down the slab.

    I hope this helps.
  8. 0
    Sudharma C. ·
    Shahul
    Thanks for the advice

    There are quite a number of cold rooms for this catering facility, the largest one the size is 33 meters in length while the width is about 11 meters.

    At the moment the interfaces or sequence of works i had worked out is as follows:
    1. Structural setdown
    2. Refrigeration piping
    3. Floor insulation installation
    4. Cold rooms (walls & ceiling)
    5. Backfilling concrete
    6. Slotted drain positions
    7. Internal screeding
    8. Epoxy floor painting
    9. 1st fix electricals
    10. 1st fix fire fighting systems
    11. 2nd fix electricals
    12. 2nd fix fire fighting systems
    13. Cooling coils unit installation
    14. Condensation piping installation
    15. Cold room door installation
    16. Bumper installation inside & outside cold room (for protection of the cold room wall panels)

    There are also interfaces with the other systems which are done by other contractors.

    rgds
    sudharma
  9. 0
    Mike Testro ·
    Hi Se

    Please assist me - I do not understand the phrase "Pull-down of slab"

    Pull-down of slab will take around 4-5 days after 28 day curing of the slab. make sure the required dehumidifiers are already working before you pull down the slab.

    Can you explain further?

    Best regards

    Mike Testro
  10. 0
    Mike Testro ·
    Hi Sudharma

    You say that there are a large number of store rooms in the catering facility and still the specialist contractor will not tell how long it will take fior them to install!

    Are they not contractually obliged to reveal their programme.

    If work has not yet started then make a condition in the tender and / or part of the prequalification document.

    If they do not tell you how long it will take then they are off the bid list.

    Best regards

    Mike Testro
  11. 0
    Sudharma C. ·
    Hi Mike
    at the moment we are going through a retendering exercise for these works.

    i am preparing an interface schedule to let the tenderers know locations of their works, when they can tentatively come in, when they need to finish to allow the other contractor to commence their work, etc....

    hence i need to be reasonable and fair with the durations and estimations that i make as to when this particular tenderer can come in and do their work.

    the easiest way to do this is to give them a start milestone as to when they will start and a finish milestone as to when they should finished.

    the main problem by doing the above, is the tenderer will not be able to identify the various/numerous interfaces they will have with the other subcontract works.

    hope the above helps in explaining why and what i am doing.
    thanks for the various feedbacks.

    rgds
    sudharma

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?