Updating P3 Programmes

Mario PatelMember for 22 years 6 months
Created
9
3
0
When you need to update a P3 programme, Do you update the Master or the sub programmes?

9 replies

Oldest first
  1. 0
    Rajesh Moolakkandam ·
    Master program is not updated usually.you have to udate the current shedule only.Master program/base program is with which you are comparing the current progress.
  2. 0
    Mk Tse ·
    Mario,
    Would you mind to explain the meaning of ’update’?
    Is it for input the progress or preparing a revision. The approach is different.
    Also you have mentioned the term ’master’ and ’sub’ of a P3 programme. P3 data structures need to be considered also.
  3. 0
    Mario Patel ·
    The Master has been devided into 3 sub programmes. I need to input new dates into the programmes to check progress or slipage.
  4. 0
    Mk Tse ·
    Except the hommack, need to review all non-complete activites for progress input.
    I would like to name the process "progress input" or "progress update" rather "update"
  5. 0
    Mario Patel ·
    So all I have to do is put the new dates in the sub progs and schedule to current date?
  6. 0
    Mk Tse ·
    Yes.
    Besides the sub-programmes, those activities in master level need to be review their progress also.
  7. 0
    Mario Patel ·
    When you say review the master,do I have to change anything in there. I thought the master and the Target are the same?
  8. 0
    Mk Tse ·
    I think there is some mis-understanding.
    In P3 programme, on data structure, there are 2 levels, one is master and the other is sub (some user will name it project and sub-project).
    To make it simple, you need to review the activities (no matter in project or sub-project).
  9. 0
    Mario Patel ·
    Thanks