FS (Baseline) >> FF (updating)
In the Open Standard
Ruy Frank RosalesMember for 19 years 10 months
- Created
- 12
- 4
0
I have been trying to analize the updates that I had been doing on the schedule that I am working on. And I have thought about this (see below). Correct me if I am wrong. I need insights as well.
Example 1: Construction = activity A
Pre-commissioning = activity B
•Most of the time in a baseline schedule A and B will be set in FS (finish to start relationship). If this is true, we can say that the finish date of A should affect the finish date of B.
•But during updating, at a certain date B can start even if A haven’t finished yet.
•As a result of the FS relationship, A’s finish date will no longer affect B’s finish date. Which is now, while updating, incoherent with the purpose of the baseline schedule.
Example 2: if A = 3 days duration
B = 3 days duration
So if A & B with FS relationship (0 days lag) = 6 days total duration
Then A & B with FF relationship (3 days lag = B) = 6 days total duration
If our goal is to determine the effect of each activity’s finish dates to the project finish date.
Query: Can I change all FS to FF with consideration to each activity’s baseline durations.
Reason: In order to monitor the effect of each activity’s updated finish dates to the project finish date.
Thanks and Best regards
Example 1: Construction = activity A
Pre-commissioning = activity B
•Most of the time in a baseline schedule A and B will be set in FS (finish to start relationship). If this is true, we can say that the finish date of A should affect the finish date of B.
•But during updating, at a certain date B can start even if A haven’t finished yet.
•As a result of the FS relationship, A’s finish date will no longer affect B’s finish date. Which is now, while updating, incoherent with the purpose of the baseline schedule.
Example 2: if A = 3 days duration
B = 3 days duration
So if A & B with FS relationship (0 days lag) = 6 days total duration
Then A & B with FF relationship (3 days lag = B) = 6 days total duration
If our goal is to determine the effect of each activity’s finish dates to the project finish date.
Query: Can I change all FS to FF with consideration to each activity’s baseline durations.
Reason: In order to monitor the effect of each activity’s updated finish dates to the project finish date.
Thanks and Best regards
12 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?