Public Holiday Dates

Gary FranceMember for 22 years 11 months
Created
8
3
0
Hi Planeteers,

As planners and schedulers, we often need to know the dates of forthcoming public holiday dates in order that these can be allowed for in our schedules.

If you need information about public holiday dates, follow this link to view a spreadsheet containing holiday dates for various countries ...... Public Holiday Dates

If you would like to add public holiday dates for a country not currently on this spreadsheet, or add further public holiday dates not currently shown, or if you are aware of any errors on this spreadsheet, then follow the instructions on the spreadsheet.

Best wishes,


Gary France
Chairman
Planning Engineers Organisation

8 replies

Oldest first
  1. 0
    Stephen Devaux ·
    Wow! Just wow!

    Thanks, Gary. I’ll make sure that my grad students add Barbados to the spreadsheet within the next three weeks!
  2. 0
    Gary France ·
    PPer’s

    I need your help.

    The PEO collects and collates public holiday dates for various countries in the world. This helps planners and schedulers know in advance what days they need to allow in their programmes / schedules for non-working periods.

    Can you click on this link and check the public holiday dates for the country you are in and advise me of any additions or changes needed?

    Thanks.

    Gary France
    Chairman
    The Planning Engineers Organisation
  3. 0
    Marcel van der Leij ·
    Gary France’s initiative is sympathetic but there exist already a very good listing:
    www.oanda.com/site/centralbanks/
    For the forensic planners amongst us, you can look up the holidays of the past 5 years.
    For the lucky planners amongst us, yes Barbados is included ;-)
  4. 0
    Chris Oggham ·
    Hi Guys,

    I checked the site Marcel mentioned for the dates of Public Holidays for the UK, Scotland and Northern Ireland. Of the thirteen Public Holidays quoted, nine were incorrect, maybe that’s why Gary is preparing his own spreadsheet.

    Regards

    Chris Oggham
  5. 0
    Ronald Winter ·
    The ultimate site for world-wide calendars (plus an interactive calendar) may be found at http://www.timeanddate.com/calendar/index.html?year=2006&country=1.
  6. 0
    Marcel van der Leij ·
    Chris,

    I did check the listing with my current location (Bulgaria) and found no mistakes.
    But, if you think about it, the number of public holidays may sometimes vary depending on where exactly you are within that country, like Germany has several lists of public holidays, depending on which Bundesstaat you live in (Catholic regions tend to have more public holidays).

    Cheers

  7. 0
    Adrienne Drew ·

    Thanks for the spreadsheet,

    Thanks for the spreadsheet, and to Stephen for updating the sheet adding Barbados.  I hope someone can also add for Bahamas, Jamaica, Antigua and St Lucia holidays as we visit often in the islands of Caribbean.

  8. 0
    Charls Lee ·

    Social Media Marketing (SMM)

    Social Media Marketing (SMM) helps to provide useful information to customers about the products and services in a casual way and also helps them with Search Engine Optimization (SEO). For B2B clients, the Marion Group can help your business by focusing your SMM efforts on Blogs, LinkedIn, Twitter and Facebook. It also helps to improve the communication by generating an online conversation through social media channels. You can build good relationships with your customer base. You need a good execution of the social media marketing Houston, as it could give you priceless returns. You need to develop a proper strategy for understanding and implementing the best practices of a particular platform, and using it thoughtfully. It will also help you to understand the community functions, its mannerisms and ethical practices. Online tools and websites enable people to communicate and share information and thus your product is marketed.