Programme Logic Vs Site Teams thinking
In the Open Standard
Shivaji NagareMember for 21 years 9 months
- Created
- 13
- 5
0
Hi everyone?
I am working on a five star multistoried Hotel.
The completion schedule (bout 4000 acts) was developed on 1st information drgs and when nobady from construction team was available.
meanwile the schedule was approved.
Now lot of changes have been made in drgs and construction team has thair own views on sequencing of job.(Job on going)
So in this case what should be done? If the programme is changed to suit site logic will be contrctually accepted?
How many time the programme should be changed??
Any wild thoughts please...
Shiva
I am working on a five star multistoried Hotel.
The completion schedule (bout 4000 acts) was developed on 1st information drgs and when nobady from construction team was available.
meanwile the schedule was approved.
Now lot of changes have been made in drgs and construction team has thair own views on sequencing of job.(Job on going)
So in this case what should be done? If the programme is changed to suit site logic will be contrctually accepted?
How many time the programme should be changed??
Any wild thoughts please...
Shiva
13 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?