out of sequence

Mac LetatMember for 21 years 1 month
Created
3
2
0
hello!!!

its my first time here, can anybody help to elaborate simply about out-of-sequence is and how we can say if the activities are in-out-of-sequence...it may cause a delay in a project? how should i solve it....

thanx for the help...
letat

3 replies

Oldest first
  1. 0
    Sen Moc ·
    Hi, Mac.

    You may visit this website: www.htcprojectcontrols.com and go to below article by Eric Chou. This will give you some insights on the subject.

    ”The Myths of "Out-of-Sequence" and "Retained Logic vs.
    Progress Override"

    (As you enter the site, go to Solution Bulletins/Primavera.)

    Regards & Mabuhay!
  2. 0
    Mac Letat ·
    Sen

    hello there...thanx pre...


    letat
  3. 0
    Sen Moc ·
    By the way, the topic on out-of-sequence has already been discussed extensively here in Planning Planet -> Forum->Primavera Project Planner P3 -> Out of Sequence Activities.

    Or you may go to below hyperlink:

    http://www.planningplanet.com/forum/forum_post.asp?Cat=2&Top=568


    Cheers!