Scheduling Practice for Oil/Gas or Pharmaceutical proje

Paul YoonMember for 22 years 1 month
Created
2
4
0
Is there anyone who willingly help/give me a sample schedule and scheduling specification for industry construction project?

Actually I have been working in a commercial building construction industry as a scheduler almost 8 years, but I have never been exposed to industry construction project like Oil/gas, pharmaceutical project and manufacturing project.

Or could you give me any idea regarding a standard scheduling specification for oil/gas and pharmaceutical project? Or could you suggest any website for me to understand that type of construction scheduling practice?

In person, I really want to know/understand the scheduling practice in another building types, mostly civil heavy or manufacturing construction. My email address is hyoonx@hotmail.com

In advance, thank you so much.

Paul

2 replies

Oldest first
  1. 0
    Zhang Haixiang ·
    Hi,

    the basic scheduling method is the same as commercial buildings. What you need is experience (e.g. production rate,relationships between systems...) There is so many kind of industry buildings with different size,I don’t think there is template available. you need study the design first then start to prepare the schedule with your team members
  2. 0
    Sriram Iyer ·
    Hello,
    For planning, the conceptual thinking is important. For that u have to go thro complete contract documents & understand scope of work.

    Some tips are as follow

    a) List out the items for the project

    b) Identify the durations

    c) Interlink the project