Progress Updates on Resourced and Duration Based Plan

Danya PearceMember for 22 years 3 months
Created
4
3
0
Hi All,

I have delevloped a schedule in MS Project incorporating engineering design and procurement activities. I have resourced the engineering and drawing office activities but obviously not resourced the procurement lead times etc as they are duration based. Can someone please give me the best method to track progress on this schedule (in excell formatt) as I will be receiving % complete on the engineeering deliverables from our document management system (based on weightings)?

Thanks

Danya

4 replies

Oldest first
  1. 0
    Sukumaran Subaramaniyan ·
    Danya,

    You can assign dummy resource to procurement schedule, i.e Man = 1. Then export the info to excel to calculate the weight and update the progress.

    HTH.
  2. 0
    Danya Pearce ·
    thanks,

    appreciate your response. will try it!!!

    All the best

    Danya
  3. 0
    Omar Grant ·
    Hi Danya - just a comment on procurement weightings: I normally score a weighting of 75% when the PO/Contract awarded, 25% to the manufacture/delivery. Cheers,
  4. 0
    Danya Pearce ·
    thanks for the advice