Progress Updates on Resourced and Duration Based Plan
In the Open Standard
Danya PearceMember for 22 years 3 months
- Created
- 4
- 3
0
Hi All,
I have delevloped a schedule in MS Project incorporating engineering design and procurement activities. I have resourced the engineering and drawing office activities but obviously not resourced the procurement lead times etc as they are duration based. Can someone please give me the best method to track progress on this schedule (in excell formatt) as I will be receiving % complete on the engineeering deliverables from our document management system (based on weightings)?
Thanks
Danya
I have delevloped a schedule in MS Project incorporating engineering design and procurement activities. I have resourced the engineering and drawing office activities but obviously not resourced the procurement lead times etc as they are duration based. Can someone please give me the best method to track progress on this schedule (in excell formatt) as I will be receiving % complete on the engineeering deliverables from our document management system (based on weightings)?
Thanks
Danya
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?