GAS PLANT PIPING (Piping Distribution)

zulfi AliMember for 21 years 11 months
Created
4
2
0
Dear Friends ,

Anybody have idea about gas plant piping.
Sulfur Recovery and treatment plant. Piping Distribution
I have been given just P &IDs and piping in tons , could you please give any idea what would be distribution of piping with their Dias in differrent medium with their sizes.
like Rich Amine, Lean Amine, Cooling water, Steam condenser, Combution Air, Sulfur Condenser

18" 20%? Lean Amine
8" 25%? Rich Amine
Cooling Water

Distribution of piping in terms of percentage just an idea.

Anxiously waiting for your reply

Thanks a lot,

4 replies

Oldest first
  1. 0
    Mohd Mahd ·
    Dear zulfi,
    P&ID’s can not be used for planning. They are to show the process components.
    To start ur planning you want piping layouts, piping GA’s.
    where u can know the distances the diameters the leveles, undergrounds, above grounds.........

    P&ID’s will help getting good idea about the subject. in rarely some cases u can create level 1 or 2 plan.
  2. 0
    zulfi Ali ·
    Right now I am in the mist of making one Proposal. This I know that P & ID good for commissioning and testing purpose, that’s why I asked any idea of piping and it’s compositon ..P & ID can not do anything for my job.
    I have tonage of piping str and supports..

    Thanks
  3. 0
    Norzul Ibrahim ·
    Dear Zulfi,

    Normally, in parallel with the P&ID preparation, we also prepare the line list that register all the line no, spec, size, fluid type, pressure, temp, etc. Can u obtain the line list?

    What is the capacity or your Sulphur Recovery Unit (SRU). I’m from the refinery and we do have SRU. Just to check, which Licensor yu are planning to use i.e. Comprimo?

    Thanks

    norzul
  4. 0
    zulfi Ali ·
    I have called one of my friend , he will let me know about the capacity of plant. I have to submit a report and dont have enoguh information from contractor....can you please let me know
    what are the general distribution of piping in a medium sized palnt..... like 20" sch 40 is 65% of the plant....18" Sch 40 10% of plant....I was given only in tons like CS piping 2400 tons.
    Any help from you can give me great bost.

    Thanks a lot Brother

Log in or join to reply