Engineering Manhours relational to Procurement Manhours
- Created
- 19
- 6
19 replies
Oldest first- 0WRWilliam Rosborough ·Hatem,
Thanks for the interest, wondering if there is a relationship between the number of Engineering MHRs and the number of Procurement MHR’s documented anywhere based on an EPC project wherein Engineering and Procurement is done by the same organization.
thanks, Bill - 0NINorzul Ibrahim ·I’m currently involve in a project (EPCC Type Contract)
1) Total estimated plan manhours = 1.7 million manhours
2) Engineering manhours = 1.3% (based on actual the engr manhours has doubled or tripled...)
3) Procurement management manhours = 4.7%
4) Construction workforce/management manhours = 76.0%
5) Commissioning workforce/management manhours = 8.0% - 0MRMehdi Rashidi Alangeh ·Dear William,
I you want some information about know- how weighting oil& Gas Projects.please contact with me by email, mehdi.rashidi@engineer.com
Also, notice that my example is output from our project but for new calculation weights of project we need project scope of work.
Best Regards
Mehdi Rashidi - 0JKJ Karthik Kumer ·
Dear Mehdi Rashidi,
Dear Mehdi Rashidi, sir,
i also working in oil & gas (epc project), i also doubt have how to assign weight to engineering, procurement, construction, commissi etc... ,
kindly send me the data for my mail id : jk_jayaraman@yahoo.com
or otherwise i will be contact to your mail id sir,
even how to (what based on values assign this -manhour,cost)
i expect the your valuable replay
- 0JIJenny Ingco ·
Dear All, I am facing same
Dear All,
I am facing same issue with my schedule which my manager asked me to review it for our clint and make some nots but the issue I don't know exactly what I should check? If someone interased I can send you the schedule and let me know...
Thank you,
- 0JIJenny Ingco ·
Dear All, I am facing same
Dear All,
I am facing same issue with my schedule which my manager asked me to review it for our clint and make some nots but the issue I don't know exactly what I should check? If someone interased I can send you the schedule and let me know...
Thank you,
- 0JIJenny Ingco ·
Dear All,I am working on Oil
Dear All,
I am working on Oil and Gas schedule and this my 1st time working on Manhours issue I use to work on Nonlaboer scheduls. I just need to know how I can calculate the Manhour I mean what formate I should use? And I appricate if someone wann take a look on my schedule and can help me to know whats the wrong data I using?
Thank you,
- 0RPRitesh Parakkal ·
What would be the Manhours
What would be the Manhours required for Engineering of a Building ( Steel Structure + Sandwich Panel) of Size 49 Mts x 13 Mts X 4 Mts height . Engineering Manhours ?
Can i refer somewhere for this Information ?
Regards
Ritesh Parakkal
riteshparakkal@gmail.com
- 0RPRitesh Parakkal ·
What would be the Manhours
What would be the Manhours required for Engineering of a Building ( Steel Structure + Sandwich Panel) of Size 49 Mts x 13 Mts X 4 Mts height . Engineering Manhours ?
Can i refer somewhere for this Information ?
Regards
Ritesh Parakkal
riteshparakkal@gmail.com
- 0RPRitesh Parakkal ·
Planning ManhoursHi All ,I
Planning Manhours
Hi All ,
I dont see any reference to Planning Manhours / Productivity for different activities on the Planning Planet. Can anybody refer me to any Websites or links where i can refer to these for my Planning and Costing activities for Oil & gas Projects like Plants , Refineries, Petrochemicals, Pipelines etc
Regards
Ritesh
Log in or join to reply