Report Formats

Rahmat HidayatMember for 24 years 2 months
Created
2
2
0
Reports is very important document for project control team in tracking the construction work performance and for the project close out. Anyway I still confuse how to get the best format for daily or weekly reports. Does anyone have experience what contents should be included in daily or weekly reports from subcontractors and construction team ?

I have many years experince in construction but usually our repots become garbage only after project close out, so give me ideas guys !

2 replies

Oldest first
  1. 0
    W A ·
    for daily:
    1) manpower for every trade, carpenets, steel fixers, etc..
    2) specific activities for today, activities for tomorrow, and activites for yesterday
    3) No, of labours for every activity, and location of the activity.
    4) equipments

    for weekly,

    1) Manpower histograme
    2) Updated programme (schedule)
    3) no. of completed activity during this week, previous week, and total todate,
    4) planned Vs actual of every major/semi-major activity as needed
    5) planned Vs actual of progress and cost, for every week and cumulative

    6)submittals status

    7) etc.., there are lot and lot of things can monitor, just start with what u knwo now, and you can enhance it further

    hope that’s help despite it is not a fully complete list.


  2. 0
    Zhang Haixiang ·
    Do not ask for too many information for the report.
    Think about what information really needed.
    Sometimes, contractors can not follow , and you will get nothing.