Scheduling work around an activitity
In the Open Standard
Nigel HusseyMember for 20 years 5 months
- Created
- 2
- 4
0
My project network has two phases, phase 1 and phase 2. Phase 1 has its own commissioning activity, which means no other activities can happen when this activity is planned to happen (simultanously). The network is structured in such away that phase two activities can happen simultanously with phase 1 as they can happen before (if time allows) or after phase 1 commissioning but not at the same time as phase 1’s commissioning activity (thus no logic connection to this activity). Having different calenders on commissioning and other will not work as one cannot know for sure when the commmissioning will take place due to any slippages in the network, calendars are not dynamic. Using resource leveling will not work either for the same reason. Hope I have explained this situation well enough. Any suggestions on this delima?
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?