Continuous Flight Piling outputs.

Alex LeitesMember for 20 years 2 months
Created
1
4
0
Can somebody please point me in the right direction of outputs for Continuous flight piling.
The piles are between 6 and 8 metres on about 3m of made up ground (gravel/sand) and the bottom 3-5 on sandstone.
Thank you.

1 reply

Oldest first
  1. 0
    Andrew Flowerdew ·
    Alex,

    What diameter are the piles and how hard is the sandstone?

    If you want advice then May Gurney Integrated Services Ltd run the largest fleet of CFA rigs in the UK and would no doubt be interested in helping. (01603 727272)

    The number of piles a day could range from a couple to ten or a dozen a day depending on the above info.