7-days calendar vs. resource loaded schedule
In the Open Standard
Bo JohnsenMember for 20 years 7 months
- Created
- 1
- 2
0
Many Owners/Clients want to have a WBS-programme submitted in calendar days, i.e. 7-days calendar. At the same time they also want a resource loaded schedule, not just names of resources, but also number of units (workers).
Doesn’t that defeat the object if the Contractor only works 5 or 6 days a week? By adding in resources the manhours will be higher than what is actually worked on site and the schedule can’t really be used for tracking of manhours - unless the Contractor have a seperate, identical schedule in working days (i.e. 5 or 6 days week in this case).
How is it possible to satisfy the Owner’s requirement and at the same time utilizing this schedule for manhours tracking purposes being the Contractor?
rgds,
Bo
Doesn’t that defeat the object if the Contractor only works 5 or 6 days a week? By adding in resources the manhours will be higher than what is actually worked on site and the schedule can’t really be used for tracking of manhours - unless the Contractor have a seperate, identical schedule in working days (i.e. 5 or 6 days week in this case).
How is it possible to satisfy the Owner’s requirement and at the same time utilizing this schedule for manhours tracking purposes being the Contractor?
rgds,
Bo
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?