Skip to content

Testing and Commissioning

Pacifico PallasiguiMember for 22 years 8 months
Created
2
2
0
Hello PP members.


I would like to seek help with regards to testing and commissioning commercial buildings. Most specially the right timing in testing the equipments and identify the activities and sequence of events.

TY

2 replies

Oldest first
  1. 0
    Mk Tse ·
    I think the equipment manuel will help. T/C is a process of operation, so all steps are listed.
  2. 0
    Dayanidhi Dhandapany ·
    T&C will commence 8-10 weeks before handing over of project. of course, you can start T&C after energising the transformer for building projects.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?