ACTIVITY LINKING?

Weni SamsonMember for 19 years 11 months
Created
7
4
0
I need some clarification regarding linking an activities. Is it possible to link an activities...say...ACT.2 has a PREDECESSOR ACT.1 of FF & SS relationship and a SUCCESSOR ACT.3 of FF & SS relationship? What’s the purpose then? Is it acceptable?

Thanks a lot.

7 replies

Oldest first
  1. 0
    Dayanidhi Dhandapany ·
    Hi Weni,

    you can have SS and FF relationship to the predecessor as well successor. the main reason to have FF rel will remove open end to the pred/succ. in your case. or else you will not get any impact during update, if there is any delay in the completion of pred. activity. it depends on the situation to use it.

    HTH

    Daya
  2. 0
    Weni Samson ·
    Thanks Mr. Dayan. You really of big help to everybody.
    Cheers!!!

    Weni
  3. 0
    David Andreotti ·
    Another good reason to have both a SS and FF relationship is so the successor won’t finish before the Predecessor finishes.
  4. 0
    Alex Wong ·
    Weni

    Sound like a hammock activity (summary) to me for Activity No1

    That way it will show the earliest start date of a group of activity and latest finish date.

    Cheers

    Alex
  5. 0
    Gilbert Liu ·
    Also not to forget u need to choose " Hammock" in the Activity Type for that activity to be a hammock for pe to have SS ad se to have FF
  6. 0
    Izam Zakaria ·
    Back to the weni question, it would be happen and u really need further study on site status...u can play aroud with lag rite???? so what is the main problem....for the hammock activities suitable for summary of activities...as highlighted before by alex....

    so weni u got what i really meant here???
  7. 0
    Weni Samson ·
    The way you replied seems impolite to me and I could’nt get it. Thanks anyway.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?