Data Date For Revised Target Plan

Razi KhanMember for 22 years 4 months
Created
2
2
0
Hi,

What would be the data date for establishing Revised Target Plan after of 6 month of progress ?



Cheers

2 replies

Oldest first
  1. 0
    Tahir Naseem PMP, CCE ·
    Dear Razi
    Salam
    The data date is the your cut of date of progress for six month.
    But keep in mind you should copy your target first to save your original base line. And after update & revision of this current plan you will get your latest forecast plan can be use as target 2.
    regards
    tahir
  2. 0
    Alex Wong ·
    Some use the baseline schedule and update the logics, duration, additions, deletions and the same datadate as the revised target.

    Otherwise as what Tahir suggested use the latest progressed schedule with all the additional information as your revised target.

    HTH

    ALex