ACTIVITIES LOGIC

Ulysses GarciaMember for 21 years 1 month
Created
3
3
0
Dear planners,

Is there any best approach in linking activities to a 3,000 task or more in the new project scheduled in order to avoid pitfalls due to illogical sequences .
Regard, uly

3 replies

Oldest first
  1. 0
    Ronald Romero ·
    Uly,

    Make a subproject template that your sure of the logic then copy this for the rest of the remaining activities or subproject in your schedule. Also use fragnet with the correct sequences. Im sure those more than 3000 schedule has some redundant activities..

    Regards,

    Ronnie
  2. 0
    Gilbert Rayco ·

    In addition to Ronald & Clive, In my practice a well organize activity coding will certainly helps in logic connection and review. Meaning it should not be too long or too short but simple and easily identified.
  3. 0
    Hazem Rady ·
    I guess the best way is :
    1. divide the project into phases or sub-projects or groups or according to responsibilties or location or whatever criteria you can divide your project to.
    3. each phase or group has it’s own inter-relations between its activities.
    2. try to make milestones or hammocks at the end of each phase that connects each phase with other phases where possible
    3. put them together and you got the 3000 act. together