Shopping Mall Programme

Dean JonesMember for 17 years 2 months
Created
5
2
0
Dear all,
i am desperately looking for a shopping mall programme for reference.

Please, if anyone of you have p3 or p6 programme for shopping mall, kindly mail that to me.

thanks in advance,


use private message servfice

5 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Dean,

    How about if we write it up here. It will take up 1-2 days from your time.

    The is level 1:

    Excavation
    Skeleton Works and E/M first fix
    Electromechanical Works
    Finishing Works
    Cladding
    Fit up period for tenants.
    Kitchens
    Toilets
    Elevators and Escalators and people movers
    Metal Works
    Wood Works
    Water features
    Landscaping
    Signage

    Give us a bit more idea about your project, and we can give you more details about what is needed to be accomplished. This will enable you to complete your Program in no time.

    With kind regards,

    Samer
  2. 0
    Shah. HB ·
    Hi

    In addition to Samer’s post ,add WBS for Testing & Commissioning
  3. 0
    Rashid Iqbal ·

    Before you start open up the project estimate, get an idea what there CBS is ..map there CBS to project WBS and the details that Samer has provided.

    It will give you most of the details that you are looking for..including details for resource loading the schedule. Thanks.


  4. 0
    Dean Jones ·
    Thanks for all the replies.
    here is my set of activities, which has to be completed in around 24 months time.
    Civil work (Structure) 12 months
    Building finishes 12 months
    Facade- Glazing
    Cornices external finishes
    Landscapping
    External works like Boundary walls and roads
    Plumbing
    Signage
    Car parking management system
    Gas bank
    Public address system
    Escalators & lifts.
    Electrical
    Firefighting
    Sewage Treat Plant
    Water Treat Plant
    DG sets
    HSD tanks for DG
    AC includes
    Access control system
    CCTV
    BMS
    lighting arrangement inside and external lighting.

    Can someone guide me which MEP activity can go parallel and with what activity.
    what kinda relationship that can be established from the given set of details.

    kindly guide me.

  5. 0
    Samer Zawaydeh ·
    Dear Dean,

    I recommend that you divide the project into:

    Main Building
    Annexes; Sewage Treatment Plant, Water Treament Plant
    Landscape Works.

    The Main Building is the Critical of course. I assume that you have several basements. Once you finish you 2nd basement from the bottom, your 1st basement formwork will be removed, and you can start your EM activities. The EM activities in the public areas will stay up to the end. Usually you have the space open for rent and the Tenants will do the EM works themselves. All you have to do is bring the networks up to their connection points.

    EM Activities can goin parallel, but usuall you have:

    1. HVAC works; marking, support system, ducting, testing, insulation.
    2. Fire Fighting works: marking, support system, ducting, testing, insulation.
    3. Plumbing
    4. LPG

    Electrial works must start with the Cable Trays, then you install the main cables and at last you do the termination of the Main Electrical Panels (Power, lightin, low current).

    Once you complete the Main Building structure, you can start with the Facade works.

    The bounday walls you can start at your earliest. It will give you site security and you will save up on the fencing.

    The people movers (escalators, etc) are long lead items. So you must get approval and order them within max 3 months period.

    The signage will not be clear until the mall is rented out and that is at the last stages.

    Hope that the information helps.

    With kind regards,

    Samer