Hotel Construction Programme - Help please
- Created
- 17
- 8
I immediately need detailed Construction Programme for Five Star Hotel having start to finish activites in pdf.
Most planners on this forum surely involved planning of such Luxury Hotel construction. Anyone can please forward me a copy of it asap.
jthorpe2008@yahoo.co.uk
Awaiting Members help.
Thanks.
James
17 replies
Oldest first- 0MTMike Testro ·Hi James
I notice that your speciality is Civil Engineering.
Believe me building is easier - I have worked in both disciplines and any sort of vertical arrangement is easier than a flat linear one.
Just look at the drawings and the spec and think the construction process through from setting out to final test and commission.
I have said many times in PP - If you can’t build it you can’t plan it.
Best regards
Mike Testro. - 0SZSamer Zawaydeh ·Dear James,
Please describe the scope of work that you have and we can provide you with all the activites in few posts.
Basic division of area; Rooms, Corridors, Ballrooms, Basements, Roofs, Landscape works, Laundry
1. Substructure
a. site layout
b. excavation
c. shuttering
d. Blinding
e. Concreting of footings + vertical elements
f. Insulation of footings
g. Protection of insulation
h. fill around footings in layers
i. blinding for slab on grades
j. insulation, reinforcement and concreting of Slab on grade
2. Super Structure.
a. Column shuttering, reinforcement and concreting.
b. Slabs shuttering, reinforcement and concreting.
c. Cladding works
3. Finishes
a. Block partitions.
b. Electromechanical 1st fix
c. Plastering.
d. Tiling works
e. Wood works
f. Electromechanical 2nd fix
g. Ceiling works + E/M 3rd fix
h. Painting works.
i. Wall paper
j. Carpet works.
k. Stainless Steel works.
l. Glass works.
m. Signage
4. Furniture and Art Works.
5. Testing and Commissioning.
Pools, Laundry, kitchens, Bars, 3rd party inspection, soft opening snags.
With kind regards,
Samer - 0SZSamer Zawaydeh ·Dear Mike,
That can be dealt with easily:
steel framed structure on a piled basement foundation:
Substructure
- Site layout
- Pile Drilling
- Pile Reinforcement
- Pile Casting
- Pile Top end preparation
- Raft shuttering, reinforcement and casting
- Column necks shuttering, reinforcement and casting.
- Fill under Slab on Grade
- Slab on grade reinforcement, Anchor bolts installation and concrete casting.
Superstructure
Structural Steel Erection (for all floors)
- Erection of Structural Steel Columns
- Erection of Beams and Bracing.
- Erection of Corrugated sheet studded slabs
- Casting of Concrete for slabs
Facade Cladding.
- Substructure
- Cover skin
- Finishes.
For the two storey villas case:
Divide the project into Zone or number of Villas. And start with the same conventional program of works. You will need to calculate the resources and make the work go in parallel from one Zone or Villa to the Other.
With kind regards,
Samer
- 0MTMike Testro ·Hi Samer
Of course you have the skill and expertise to do it from the top of your head - you can build it therefore you can plan it.
Unfortunately you missed my point.
The chap who started this thread has never built a hotel in his life.
He will never do it from a single template - no matter how expertly detailed the advice.
Why not ask him for the drawings and spec and do the plan for him.
I have just finished a 4 storey hotel programme - it took me 6 hours Bottom Uo - fully resourced.
Best regards
Mike Testro
- 0SZSamer Zawaydeh ·Dear Mike,
We are just assisting him in starting up his schedule. I really believe that each person should build up his own schedule. Sometimes you need a small push forward. So this was it, no more. Cutting and pasting templates/ old schedule will only put a person out of touch with the project.
I do believe that if he is serious, it might take him at least 3-4 weeks to build up a complete schedule.
I hope that he benefit from this thread. This is what it is all about.
With kind regards,
Samer - 0CPChristopher Paulraj ·
Hi can you send me also the
Hi can you send me also the hotel project schedule to my mail christosathya@yahoo.com.
- 0CPChristopher Paulraj ·
Hi Mike Testro Can you
Hi Mike Testro
Can you please send me your Hotel progarmme to my email christosathya@yahoo.com
As i dont have any experience in hotel project, can you please send me your programme.
Rgds
Chris
- 0ASAnning Sofi ·
Each project is unique. I
Each project is unique. I recommend, build the plan with your operations/construction management team.
Programmes of other hotels (that will be shared to you) do not really show the assumptions made in the plan development, procurement considerations, logistics, design and engineering etc.