Skip to content

Hotel Construction Programme - Help please

James ThorpeMember for 17 years 4 months
Created
17
8
0
Dear All,

I immediately need detailed Construction Programme for Five Star Hotel having start to finish activites in pdf.

Most planners on this forum surely involved planning of such Luxury Hotel construction. Anyone can please forward me a copy of it asap.

jthorpe2008@yahoo.co.uk

Awaiting Members help.

Thanks.
James





17 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi James

    Getting a pdf of someone elses programme will not help.

    Every hotel is different.

    You must start your own programme from the information that you have in front of you.

    Best regards

    Mike Testro
  2. 0
    James Thorpe ·
    Thanks Mike for your advice.

    Regards,

    James
  3. 0
    Mike Testro ·
    Hi James

    I notice that your speciality is Civil Engineering.

    Believe me building is easier - I have worked in both disciplines and any sort of vertical arrangement is easier than a flat linear one.

    Just look at the drawings and the spec and think the construction process through from setting out to final test and commission.

    I have said many times in PP - If you can’t build it you can’t plan it.

    Best regards

    Mike Testro.
  4. 0
    James Thorpe ·
    Mike,

    No worries. I got your point.

    Thanks a lot.

    James
  5. 0
    Samer Zawaydeh ·
    Dear James,

    Please describe the scope of work that you have and we can provide you with all the activites in few posts.

    Basic division of area; Rooms, Corridors, Ballrooms, Basements, Roofs, Landscape works, Laundry

    1. Substructure
    a. site layout
    b. excavation
    c. shuttering
    d. Blinding
    e. Concreting of footings + vertical elements
    f. Insulation of footings
    g. Protection of insulation
    h. fill around footings in layers
    i. blinding for slab on grades
    j. insulation, reinforcement and concreting of Slab on grade

    2. Super Structure.
    a. Column shuttering, reinforcement and concreting.
    b. Slabs shuttering, reinforcement and concreting.
    c. Cladding works

    3. Finishes
    a. Block partitions.
    b. Electromechanical 1st fix
    c. Plastering.
    d. Tiling works
    e. Wood works
    f. Electromechanical 2nd fix
    g. Ceiling works + E/M 3rd fix
    h. Painting works.
    i. Wall paper
    j. Carpet works.
    k. Stainless Steel works.
    l. Glass works.
    m. Signage

    4. Furniture and Art Works.

    5. Testing and Commissioning.
    Pools, Laundry, kitchens, Bars, 3rd party inspection, soft opening snags.

    With kind regards,

    Samer
  6. 0
    Mike Testro ·
    Hi Samer

    Thats a great list - but what if it is steel framed structure on a piled basement foundation?

    Or a series of two storey villas around a central reception zone in a landscaped beach environment.

    Best regards

    Mike Testro
  7. 0
    Samer Zawaydeh ·
    Dear Mike,

    That can be dealt with easily:

    steel framed structure on a piled basement foundation:

    Substructure
    - Site layout
    - Pile Drilling
    - Pile Reinforcement
    - Pile Casting
    - Pile Top end preparation
    - Raft shuttering, reinforcement and casting
    - Column necks shuttering, reinforcement and casting.
    - Fill under Slab on Grade
    - Slab on grade reinforcement, Anchor bolts installation and concrete casting.

    Superstructure
    Structural Steel Erection (for all floors)
    - Erection of Structural Steel Columns
    - Erection of Beams and Bracing.
    - Erection of Corrugated sheet studded slabs
    - Casting of Concrete for slabs

    Facade Cladding.
    - Substructure
    - Cover skin
    - Finishes.

    For the two storey villas case:

    Divide the project into Zone or number of Villas. And start with the same conventional program of works. You will need to calculate the resources and make the work go in parallel from one Zone or Villa to the Other.

    With kind regards,

    Samer


  8. 0
    Mike Testro ·
    Hi Samer

    Of course you have the skill and expertise to do it from the top of your head - you can build it therefore you can plan it.

    Unfortunately you missed my point.

    The chap who started this thread has never built a hotel in his life.

    He will never do it from a single template - no matter how expertly detailed the advice.

    Why not ask him for the drawings and spec and do the plan for him.

    I have just finished a 4 storey hotel programme - it took me 6 hours Bottom Uo - fully resourced.

    Best regards

    Mike Testro


  9. 0
    Samer Zawaydeh ·
    Dear Mike,

    We are just assisting him in starting up his schedule. I really believe that each person should build up his own schedule. Sometimes you need a small push forward. So this was it, no more. Cutting and pasting templates/ old schedule will only put a person out of touch with the project.

    I do believe that if he is serious, it might take him at least 3-4 weeks to build up a complete schedule.

    I hope that he benefit from this thread. This is what it is all about.

    With kind regards,

    Samer
  10. 0
    Mike Testro ·
    Hi Samer

    You are a very kind and thoughful person.

    Long may you contribute to PP.

    Best regards

    Mike Testro
  11. 0
    Gary Whitehead ·
    Hi James,

    Would you happen to know a Bob Benham by any chance? or John William?
    How about Chris Danniel or George William?
  12. 0
    Solo Ma. ·
    Check this from PP

    http://www.planningplanet.com/rates/rates_wbs.asp
  13. 0
    Christopher Paulraj ·

    Hi can you send me also the

    Hi can you send me also the hotel project schedule to my mail christosathya@yahoo.com.
     

  14. 0
    Christopher Paulraj ·

    Hi Mike Testro   Can you

    Hi Mike Testro

     

    Can you please send me your Hotel progarmme to my email christosathya@yahoo.com

    As i dont have any experience in hotel project, can you please send me your programme.

     

    Rgds

    Chris
     

  15. 0
    Antonio Hernandez ·

    Hi every one, I'm studing the

    Hi every one,

    I'm studing the program for a five star hotel, around 400 rooms, 24 storage.

    Would you please share with me any of your Hotel Project Schedule to get more ideas?

    My mail isuse private message service

    Thanks in advance!

  16. 0
    Mike Testro ·

    Hi Antonio Please read the

    Hi Antonio

    Please read the whole thread and then understand why sending you a sample programme will not help.

    Best regards

    Mike Testro

  17. 0
    Anning Sofi ·

    Each project is unique. I

    Each project is unique. I recommend, build the plan with your operations/construction management team.

    Programmes of other hotels (that will be shared to you) do not really show the assumptions made in the plan development, procurement considerations, logistics, design and engineering etc.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?