Job Steps For all Equipments for scheduling
In the Open Standard
Suresh Sankarankutty PMPMember for 20 years 2 months
- Created
- 0
- 2
0
Hi Everyone,
Kindly write down the job steps for Planning & Scheduling for the equipments O/H which you know.
eg: Vessel O/H
1. Isolation
2. Drain
3. Scaffolding
4. Blinding
5. Purging
6. Inspection
7. Open Manways
8. Internal Lighting and Air Educator
9. Internal Cleaning / Buffing etc
9. Inspection
10.Boxup
11.Remove Scaffolding
12. Deblinding
13. Commissioning
I think it will help many of us to refer. IF you can keep the usual estimated hours, it will be more helpful.
Thanks everyone
Kindly write down the job steps for Planning & Scheduling for the equipments O/H which you know.
eg: Vessel O/H
1. Isolation
2. Drain
3. Scaffolding
4. Blinding
5. Purging
6. Inspection
7. Open Manways
8. Internal Lighting and Air Educator
9. Internal Cleaning / Buffing etc
9. Inspection
10.Boxup
11.Remove Scaffolding
12. Deblinding
13. Commissioning
I think it will help many of us to refer. IF you can keep the usual estimated hours, it will be more helpful.
Thanks everyone
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?