Job Steps For all Equipments for scheduling

Suresh Sankarankutty PMPMember for 20 years 2 months
Created
0
2
0
Hi Everyone,

Kindly write down the job steps for Planning & Scheduling for the equipments O/H which you know.

eg: Vessel O/H

1. Isolation
2. Drain
3. Scaffolding
4. Blinding
5. Purging
6. Inspection
7. Open Manways
8. Internal Lighting and Air Educator
9. Internal Cleaning / Buffing etc
9. Inspection
10.Boxup
11.Remove Scaffolding
12. Deblinding
13. Commissioning

I think it will help many of us to refer. IF you can keep the usual estimated hours, it will be more helpful.

Thanks everyone