No of Days in Summary (in Ver 5.0)

Q.M. IsmaelMember for 19 years 7 months
Created
2
2
0
i have 3 Activity in the Group All are Finish to Start,

the duration is 20, 10, & 60, But in the summary it show the duration as 265 why is this itas has to the duration as 90 days, please advice,

thank in advance,

Qutab

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi
    these are working days. All summaries use the default calendar, your activities have a different one. If you’ll display start- and finish-dates, start of your first and end of your last activity should be the same as start and finish of the summary.

    Regards
    Dieter
  2. 0
    Q.M. Ismael ·
    Thank You, It works,

    I Change my Default Calander as Activity Calander.


    Thankyou Once again