Skip to content

number of days/Productivity norms

Vrinda MMember for 18 years 4 months
Created
14
7
0

What is the value of Bulk excavation per day ??

Anybody having productivity norms for substructure activities shoring,piling,earthworks etc???


Regards
Vrinda.

14 replies

Oldest first
  1. 0
    Milind Pandhare ·
    HI VRINDA
    WHT NORM YOU REQUIRED
  2. 0
    A D ·
    It’s all there under the rates section in this forum.

    If u want anything else, plz do let us know

    Ravi
  3. 0
    Vrinda M ·
    I would like what is the amont of bulk excavation carried out per day,In this forum under the rates bulk excavation given as %.The total bulk excavation 14000 m3 how many days it would require.

    Also please advise on dewatering,shoring whn it is carried out and hw many days it takes depending on which factors???


    Thanks fr ur help
    Vrinda
  4. 0
    A D ·
    It depends on how many excavators u want to deploy and what is ur contract duration. Howver, as a thumb rule, if u r doing excavation for a trench and location is within UAE, then with a normal excavator of 0.5m3 bucket capacity, we consider 28m3/hr as standard productivity rate.

    Check the drawings first. If depth is more, then apply some efficieny factor too.

    You may please get book on Construction equipment management by peurifoy to study further. (Approx. AED 550/-)

    Dewatering depends on the water table. Ur Consultants must have carried out geotechnical investigation. Get the report and check the water table and compare with ur drawings.
  5. 0
    Mike Testro ·
    Hi Vrindra

    Its not just the capacity of the digger - its also the haul away rate that has to be calculated.

    This depends on:

    Nr and capacity of the haul trucks - allow about 10% for bulking.

    Haul disnce in Km * 2 for return * kph = turn round time

    + 10 mins each for load and tip = m3/hr for haulage.

    This should be marginally shorter than the digger output so you have one truck waiting.

    Best regards

    Mike Testro
  6. 0
    Milind Pandhare ·
    Dear Vrindra ,
    I have one excel sheet with
    the Output rate for Excavators (Different Model )
    Dozers ,Showel ,Graders sort of Earthwork Machinary
    thease output rates are for Gulf region
    email me on
    ..............
    i will send you that file
  7. 0
    Mike Testro ·
    Hi Milind

    You should use the PP message service for this type of contact so send your email address to vrindra by that route.

    Otherwise you will be subject to the usual feeding frenzy of "me too please".

    Best regards

    Mike Testro
  8. 0
    Vrinda M ·
    Thanks,Milind,

    My email is vrindamirchandani@yahoo.com.

    Also I wanted some more info.....

    There is a G+1 office building...
    where GF is insitu slab

    but 1f & roof slabs are Post-tensioned slabs...

    What will be the construction for 1F & roof slabs,corewall etc in my programme as for Gf-Shuttering,Rebar,Concrete...
    Please advise on P.T slabs...


    Thanks,
    Vrinda

  9. 0
    Biswaranjan Behera (Ranjan) ·

    Hi Milind, Can you send me

    Hi Milind,

    Can you send me that file too @ biswaranjanbehera@gmail.com

    Regards.

  10. 0
    Vimal Kumar ·

    Hi Milind, Could you please

    Hi Milind, 

    Could you please send me the details to vimalkc3@gmail.com

  11. 0
    Sunil Thyparambil Abdul Salam ·

    Dear all,Could any one have

    Dear all,

    Could any one have productivity norms for earthworks substructure activities shoring,piling,earthworks including storm line, sewer line, low voltage medium voltage etc. Please forward me to my email id at (use private message service)

    Regards,

    Sunil

  12. 0
    Muthukumar Santhanam ·

    Dear Mr. Milind Pandhare,Sir,

    Dear Mr. Milind Pandhare,

    Sir, I am in need of producivity norms of equipments includes excavator, Dozers ,Showel ,Graders, transit mixers, rock breaker, rollers and cranes , other civil equipments . 

    producivity norms of civil manpower and structural manpower includes carpenter,fitter, mason, steel fitter,welder, rigger, all helpers. Pls send xcel format if you have ..........  

  13. 0
    Muthukumar Santhanam ·

    Dear Mr.Milind Pandhare,Sir,

    Dear Mr.Milind Pandhare,

    Sir, I am in need of producivity norms of equipments includes excavator, Dozers ,Showel ,Graders, transit mixers, rock breaker, rollers and cranes , other civil equipments .

    producivity norms of civil manpower and structural manpower includes carpenter,fitter, mason, steel fitter,welder, rigger, all helpers. Pls send xcel format if you have ...,,,,

  14. 0
    Gary Whitehead ·

    Milinde made this offer 4 1/2

    Milinde made this offer 4 1/2 years ago. I'm locking this thread to avoid any more "me too" replies.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?