Prison construction

Mohammed ShafiqMember for 19 years 8 months
Created
2
2
0
Can someone please help me out as I am looking for a programme to show me logic and terminology used in preparing a programme for building a prison.

2 replies

Oldest first
  1. 0
    Andrew Pearce ·
    Go directly to jail do not collect 200pounds.

    Nah thats Monopoly!

    Follow the usual planning steps, I presume this is a new prison.

    Look at the drawings, establish a logical sequence of construction. Evaluate the key quantities and assign outputs in order to calculate durations.

    If working within a prison site you will need to consider security constriants that will affect progress.
  2. 0
    Rod Sobarzo ·

    Prisons - Benchmark Hi, I

    Prisons - Benchmark

    Hi, I would like to create a benchmark for prisons -   construction months  and number of beds built

    If anybody has some experience and wants to share will be great , thanks , RS  